M6-S1 — Capstone I: version 1.1, the decided change in every document

Section titled “M6-S1 — Capstone I: version 1.1, the decided change in every document”
ModuleM6 — Capstone
After this session you canTake a decided change into every document it touches, so the sponsor, the builder and the tester each find it where they look, and nothing the change did not touch has moved.
TimeFacilitated: 52 min · On your own: 52 min
Before you startYour binder at the end of Part 5 (M5-S1): BRD 1.0, PDD 1.0, blueprint 1.0, the complete matrix, the CR register, the CR-01 form parts 1 to 7 and decision D-13. The BRD and blueprint template. The capstone rubric.
Your binderSo far: everything above. This session adds: BRD 1.1 (A0, A2, the register’s 1.1 rows, C4 change log), three CR-01 criteria, the matrix rows CR-01 changed, the register at Done; PDD 1.1 and blueprint 1.1 from the hand-out.
Go deeperCustomer support system tutorial (the build a blueprint like yours produces)

◆ Orientation (1 min) — One change, every document

Section titled “◆ Orientation (1 min) — One change, every document”

Thursday of week 8, Mariam approved CR-01; your communication note promised version 1.1 “next week”. This is that week. A decided change is not finished until every document that carries it says so, and says it the same way: the BRD the sponsor signs, the process definition Salma approves, the blueprint Rania builds from, the criteria the testers run, and the matrix that ties them together. Just as important is what does not move: every line CR-01 did not touch stays exactly as Mariam signed it in week 3. You write the BRD side of 1.1 yourself; the blueprint and process rows come from the reference binder, and you check that they say only what was decided.

The rubric that grades your binder at the sign-off is on the assessment page. Read its rows before you start.

★ Capstone (46 min) — Integrate CR-01: BRD 1.1, change log, register, matrix

Section titled “★ Capstone (46 min) — Integrate CR-01: BRD 1.1, change log, register, matrix”

Goal. Version 1.1 of the binder, with CR-01 in every document it touches, and a change log that says what changed and what must be tested again.

Before you start. Your binder and the CR-01 form, open side by side. Each document keeps its own version line: the BRD goes from 1.0 to 1.1, the process definition from 1.0 to 1.1, the blueprint from 1.0 to 1.1. They happen to meet at 1.1 because CR-01 is the first change to each.

Steps.

  1. A0, document control. Set the version to 1.1 and the date to week 9. List the sub-documents with their own versions. Add an approvals row for 1.1: Mariam signs it, and her signature becomes decision D-14.
  2. A8, the register. Write the 1.1 rows. NF-03 keeps its ID: write its new wording, what it was, and why it changed. F-18 and F-19 are new needs, so they get new IDs, with source, F or NF, priority, reason and release. Never renumber or reuse an ID.
  3. C1, three criteria. Write AC-NF03b (a Priority ticket’s limit), AC-18a (the account manager is told, with a negative half) and AC-19a (the desk’s Priority counter).
  4. C2, the matrix. Update rows NF-03 and P1b, add rows F-18 and F-19 with every column filled, and write CR-01 in Changed by on each row it altered or now relies on.
  5. File the hand-out below: the blueprint 1.1 rows, PDD 1.1, the other BRD sections and the other CR-01 criteria. Check each line against form parts 4 and 7: a line that goes further than Option A is a change nobody decided; a part of Option A that no line carries is a gap.
  6. C4, the change log. One row for 1.1: the change requests it carries, the sections changed in each document, whether anything is expensive for records already stored, and the criteria to write and to run again.
  7. C3, the register. Move CR-01 to Done, with the versions it went into.
  8. A2, the summary, last: half a page for someone who reads nothing else. The problem, what the system will do in each release (CR-01 included), and the decisions asked of the sponsor.
  9. Run both checks again on the four rows you changed: each has design and criteria, and each new design element names a requirement.

Check.

  • Each document has its own version line, and A0 lists the sub-documents with their versions.
  • NF-03 keeps its ID and records what changed and why; F-18 and F-19 have new IDs; no ID is reused.
  • The three criteria name people and results, and AC-18a says who is not told.
  • The matrix has rows F-18 and F-19, and CR-01 in Changed by on every row it altered or relies on.
  • The change log names the sections changed, the cost on stored records, and the criteria to write and rerun.
  • Nothing in the hand-out goes beyond what Mariam decided, and nothing CR-01 did not touch has changed.
  • The summary fits on half a page and names the decisions asked of the sponsor.

Pass condition. All seven boxes are ticked. Keep the binder: M6-S2 reviews it, and it is the evidence for your sign-off.

If something goes wrong

What you seeWhat to do
You gave the changed NF-03 a new IDThe need is the same (“picked up in time”), only its figure changes for some tickets: keep the ID and record the change. A new need gets a new ID.
Only NF-03’s row says CR-01P1b’s design now sets a limit, and F-18 and F-19 exist because of CR-01. Changed by lists every row a change altered or relies on.
Your change log says “expensive”Two optional fields and a mapped field are added, and one step’s limit changes its method; no step is added, removed or moved, and Release 2 is not live. Check against the “decide early” table in M2-S1.
The hand-out has a line you cannot find in part 4Check part 7 and D-13 first. If neither says it, it is an undecided change: take it out, or log it as a new request.
Your summary lists every section that changedThat is the change log’s job. The summary says what the system does and what the sponsor is asked to confirm.
A1 or A3 from version 1.0 looks weak to you nowLeave it: 1.1 carries CR-01 only. An improvement you want is a new request, or a note for the next version.

Hand-out 1: blueprint 1.1, the CR-01 rows (from the reference binder)

Section titled “Hand-out 1: blueprint 1.1, the CR-01 rows (from the reference binder)”

B2, Support Tickets, two new fields

FieldTypeRequiredFilled in byReq.Note
Account manager (R2)Mapped Field—The systemF-19See B5. So a notification can reach him.
Late at desk (R2)Category: YesNoThe systemNF-03, F-18, SM-5Set when the desk’s limit is missed (B9 L7). Empty means not late.

B5, one new mapped field

Mapped fieldOnFollowsSource fieldUpdate ModeReasonReq.
Account managerSupport TicketsCustomer accountAccount managerFrom Parent OnlyWhen an account changes manager, its open tickets follow the new one.F-19

B7, two field-rule rows (ticket workflow): Account manager and Late at desk are Hidden at Open Ticket, Locked at Help Desk and Manager Approval, Hidden at Processing Ticket and Service Evaluation.

B8, the Help Desk row

StepLimitMethodWhen lateReq.
Ticket · Help Desk4 working hours; 2 for a Priority accountA formula on Account tier (2 when Priority, otherwise 4; the builder writes it), Fallback Value 4 for tickets with no accountAs in 1.0 (L1, L2); and at the deadline, set Late at desk (L7) and, for Priority, tell the Account manager (L8)NF-03, SM-2, F-19, SM-5

Why a formula and not a field the desk sets. The deadline is fixed when the ticket reaches Help Desk. A value the desk sets after that moment cannot change it, so the limit must come from something already on the ticket when it arrives: the Account tier (D-07).

B9, two new automations

No.NameEventAction or recipientsValue or messageReq.
L7Mark lateOn Time Exceeded Help Desk, at the deadlineUpdate Late at deskYesNF-03, F-18, SM-5
L8Priority late, account managerOn Time Exceeded Help Desk, at the deadline, only when Account tier is PriorityAccount managerA ticket of your Priority client is waiting past its timeF-19

B10, three new queries

NameConditions in wordsUsed byReq.
Priority waiting at the deskCurrent step is Help Desk and Account tier equals PriorityThe desk’s Priority counterF-18
Priority late this monthAccount tier equals Priority and Late at desk equals Yes and created on or after @StartOfMonthThe Priority figureSM-5, NF-03
My accounts’ open ticketsAccount manager equals @me and current step is not the final stepAccount managers’ viewF-19

B11, one figure and one counter. Summary Priority tickets late this month: source Priority late this month, Count, shown as a Number on the support manager’s page (SM-5). Counter Priority waiting on Incoming Requests, counting Priority waiting at the desk, seen by everyone who may open that view: the desk and the support manager (F-18).

B12, one audience and one hand-off line. Account managers (Release 2): the My accounts’ tickets view, open to the account managers, source My accounts’ open tickets, Table view; phone useful. See the open tickets of their own accounts; act on none; told L8. Hand-off list, line 1: a group Account Managers, if the view is offered to a group rather than to named people.

Hand-out 2: PDD 1.1, Ticket handling with escalation (from the reference binder)

Section titled “Hand-out 2: PDD 1.1, Ticket handling with escalation (from the reference binder)”
  • Section 1, document control: version 1.1, week 9, approved by Salma Idris; “CR-01: the Priority pickup limit and the account manager’s escalation (sections 4, 6, 7, 8, 9)”.
  • Section 4, roles: a new row, Account manager (Karim Haddad and colleagues, Release 2): is told when a ticket of a Priority account is late, and calls the client.
  • Section 7, rule BR-6: “The desk acts on a ticket within 4 working hours of its arrival at the desk; within 2 working hours for a ticket of a Priority account. Claiming alone does not stop the clock (D-11). The limit is fixed when the ticket arrives: a later change of tier does not move it (D-07).” Section 6 refers to BR-6 at step T3, so it changes through the rule.
  • Section 8, escalation ladder: the desk’s row reads “4 h; 2 h for Priority”; a new row, “The desk, Priority account: 2 h; at the limit, the account’s manager is told, in addition to the line above” (F-19).
  • Section 9, measures: a new row, SM-5: Priority tickets the desk acts on within 2 working hours; target 9 in 10; from the tickets’ time records and the Priority figure.
  • Section 12, change history: “1.1 · CR-01 · sections 4, 6, 7, 8, 9 · account manager role added; Priority pickup limit of 2 working hours; the account manager is told when one is late; measure SM-5”.

On the to-be map, CR-01 adds one lane (the account manager) and one dotted escalation line from the desk’s wait; no task changes.

Hand-out 3: the other BRD 1.1 sections and criteria (from the reference binder)

Section titled “Hand-out 3: the other BRD 1.1 sections and criteria (from the reference binder)”
  • A3: objective O-2 extended: “New tickets are picked up quickly and predictably, faster for Priority accounts.” SM-2 as before; SM-5: nine in ten tickets of Priority accounts are picked up within 2 working hours (from Release 2).
  • A4: in scope for Release 2, also F-18, F-19 and the Priority limit of NF-03. Interim until Release 2: the desk looks at Priority clinics first by name, no change to the system. Later: an urgency other than the account tier (D-05); a quarterly satisfaction survey for clinics (J4, Ziad Amin).
  • A5: account managers (Release 2): told when a Priority ticket of their account is late; see their accounts’ open tickets; main need, to act before the client complains.
  • A10: R-7. A contact of a Priority account opens a ticket without choosing the account, so it gets the 4-hour limit and the account manager is never told. Affects O-2 and SM-5. Owner Yusuf Darwish. Response: the account is the first choice on the ticket form; the desk checks it when it claims a ticket; SM-5 is reviewed monthly.
  • A11: D-12 (PDD 1.0 approved by Salma Idris, Thursday week 6), D-13 (CR-01 approved), D-14 (BRD 1.1 signed by Mariam Khalil, week 9). No open questions.
  • AC-NF03c (negative). Given an account with tier Standard, when its ticket reaches the desk, then its limit is still 4 working hours.
  • AC-NF03d (no account). Given Customer Two has no account, when her ticket reaches the desk, then its limit is 4 working hours.
  • AC-18b. Given Karim Haddad is signed in, when he opens his accounts’ tickets, then he sees the open tickets of his accounts only, and has no action on any of them.
  • AC-SM5a. Given Priority tickets this month, some acted on late, when Support Manager opens the Priority figure, then it shows how many were late at the desk.
Model answer

A0. Document control

Version1.1, signed
DateWeek 9
Sub-documentsPR-01 Ticket handling with escalation, version 1.1 · Blueprint version 1.1 · Traceability matrix (C2) with CR-01 · CR register (C3)
VersionApproved byDate
1.0Mariam KhalilThursday, week 3
1.1Mariam KhalilWeek 9 (D-14)

A8. The register’s 1.1 rows

IDRequirementF/NFSourcePriorityReasonChange
NF-03The desk picks up a new ticket within 4 working hours, or within 2 working hours for a ticket of a Priority account.NFB Q5; SM-2; J1; CR-01Should (Standard) · Must (Priority, Release 2)Priority clinics pay for a faster service (J1).Changed by CR-01; was “within 4 working hours”.
F-18The desk sees at a glance how many tickets of Priority accounts are waiting to be picked up.FJ5; CR-01Should“Deal with my Priority clinics first” (J5, merged into CR-01).New, Release 2.
F-19When a ticket of a Priority account is not picked up in time, the account’s manager is told.FJ1; CR-01MustSo the account manager can call the clinic first (J1).New, Release 2.

C1. Your three criteria

  • AC-NF03b. Given Cedar Dental Clinic is Priority, when its ticket reaches the desk on Thursday at 15:00 and nobody acts, then it turns overdue on Sunday at 09:00 (2 working hours), not at 11:00.
  • AC-18a. Given a Priority ticket of Cedar Dental Clinic turns overdue at the desk, then Karim Haddad has a message naming the ticket and the clinic; and given a Standard ticket turns overdue, then he has none.
  • AC-19a. Given two Priority tickets and three Standard tickets waiting at the desk, then the desk’s Priority counter shows 2, and selecting it lists those two.

C2. The matrix rows CR-01 changed (new text in bold)

IDRequirementPriority · releaseSourceDataProcess and flowPeople seeAcceptanceChanged by
NF-03Desk acts within 4 working hours (2 for Priority)Should · R1 (Must for Priority, R2)B; SM-2; J1B2 Account tier, Late at deskPDD BR-6, escalation; B8 Help Desk (formula); B9 L1, L2, L7B10 Waiting at the desk, Priority late this month; B11 counter, the Priority figureAC-NF03a, AC-NF03b to AC-NF03d, AC-SM5aCR-01
P1bThe ticket shows account and tierMust · R2G P1B2 Customer account, Account tier; B5 From Parent OnlyB7 Open Ticket rules—AC-P1b-a, AC-P1b-bCR-01 (its tier now sets the limit)
F-18Desk sees Priority tickets waitingShould · R2J5B2 Account tier—B10 Priority waiting at the desk; B11 counter Priority waitingAC-19aCR-01
F-19Account manager told when a Priority ticket is lateMust · R2J1B2 Account manager; B5 mapped, From Parent OnlyPDD escalation ladder; B8 Help Desk; B9 L8B10 My accounts’ open tickets; B12 account managersAC-18a, AC-18bCR-01

C4. The change log

VersionDateChange requestsSections changedExpensive for stored records?Criteria
1.1Week 9CR-01BRD A0, A2, A3, A4, A5, A8, A10, A11, C3, C4. PDD 4, 6, 7, 8, 9, 12. Blueprint B2, B5, B7 to B12. Matrix rows NF-03, P1b, F-18, F-19.No: two optional fields and a mapped field are added to Support Tickets; the Help Desk step’s limit changes its method; no step is added, removed or moved. Release 2 is not live yet.New: AC-NF03b, AC-NF03c, AC-NF03d, AC-18a, AC-18b, AC-19a, AC-SM5a. Rerun: AC-04a, AC-05a, AC-10a, AC-11a, AC-NF03a, AC-P1b-a, AC-P1b-b.

C3. The register line. CR-01: status Done; decision “Approved, Option A, for Release 2 (D-13) · Mariam Khalil · Thursday week 8”; version “BRD 1.1, blueprint 1.1, PDD 1.1”.

A2. The summary

Bayt Devices receives about 400 support requests a month by phone and email; requests are lost or answered twice, nobody knows who handles them, and the managers have no figures. This document specifies a customer support system on Osos in which customers open numbered tickets from the web or a phone, the desk claims and routes each one, every solution is checked before it reaches the customer, refunds and replacements need the support manager’s approval, and every step has a time limit in working hours with an escalation. Release 1 (week 10) replaces the pilot and the spreadsheet.

Release 2 (week 18) adds business accounts with a service tier, site visits approved by the support manager, a public pre-sales form, and, from change request CR-01, a 2-hour pickup for Priority accounts with their account manager told when one is late.

Decisions asked of the sponsor: the pickup and solving limits (4 and 16 working hours; 2 for Priority) and their escalations; that customers see only their own tickets and office managers their account’s; that tickets keep the pilot’s way in (the Ticket Request screen) rather than becoming a catalog service.

Your wording can differ. The register rows pass if NF-03 keeps its ID with its history and the two new needs have new IDs; the matrix passes if every CR-01 element appears in a row and every changed row names CR-01.

✓ Practice (4 min) — Check your understanding

Section titled “✓ Practice (4 min) — Check your understanding”
PracticeChoose one answer.

What belongs in the half-page summary (A2) at the top of the BRD?

  1. Explanation for A

    ✓ Correct

    Correct: the summary is for the reader who reads nothing else, and who must act on it. See the model summary.

  2. Explanation for B

    ✗ Incorrect

    Not this one: detail belongs in the blueprint; the summary gives the business view in a few lines. See Two documents.

  3. Explanation for C

    ✗ Incorrect

    Not this one: that list is the change log’s job (C4); the summary says what the system does. See the steps.

Check your answer

The correct answer is A. Open the explanation under each option to see why.

PracticeChoose one answer.

CR-01 changes NF-03’s figure for Priority tickets and adds the account manager’s message. How do the register’s IDs change?

  1. Explanation for A

    ✗ Incorrect

    Not this one: the need is the same, picked up in time, so it keeps its ID and records its change. See Step 4 of a change request.

  2. Explanation for B

    ✗ Incorrect

    Not this one: IDs never change, because the matrix, the criteria and the decisions all refer to them. See the steps.

  3. Explanation for C

    ✓ Correct

    Correct: a changed figure of the same need keeps the ID; a new need gets a new one, never reused. See the steps.

Check your answer

The correct answer is C. Open the explanation under each option to see why.

PracticeChoose every answer that applies.

After CR-01, which rows of the matrix name CR-01 in their Changed by column? Select all that apply.

  1. Explanation for A

    ✓ Correct

    Correct: the change altered this row’s requirement, design and criteria, so it is listed there. See The two checks.

  2. Explanation for B

    ✓ Correct

    Correct: its wording did not change, but CR-01 now relies on its design, so a later change to P1b must look at CR-01. See Reading a change across the matrix.

  3. Explanation for C

    ✓ Correct

    Correct: new rows record the change that created them, so their origin stays visible. See the steps.

  4. Explanation for D

    ✗ Incorrect

    Not this one: a rerun is listed in the change log; F-04’s requirement and design did not change. See the steps.

Check your answer

The correct answers are A, B and C. Open the explanation under each option to see why.

You have version 1.1: one decided change, carried into the BRD, the process definition, the blueprint, the criteria and the matrix, each on its own version line, with a change log that tells the builder what to build and the tester what to run again. Everything CR-01 did not touch is still exactly what Mariam signed.

Next. In M6-S2 you read the whole binder as Rania will, with a partner or on your own, and prepare it for your sign-off.