M5-S1 — Acceptance, traceability and planning a change
Section titled “M5-S1 — Acceptance, traceability and planning a change”| Module | M5 — Acceptance and traceability |
| After this session you can | Give every requirement a test the delivered system passes or fails, prove with one table that nothing was forgotten and nothing was added unasked, and bring a change request to its owner sized, with a recommendation. |
| Time | Facilitated: 84 min · On your own: 81 min |
| Before you start | Your binder at the end of Part 4: BRD 1.0 with its user stories (A9, M1-S2), blueprint 0.9, the traceability matrix up to its “people see” column, and the CR-01 form, parts 1 to 4 (M3-S3, M4-S2). The case file, the traceability job aid and the change-request job aid. |
| Your binder | So far: BRD 1.0 (signed), PDD 1.0, blueprint 0.9 (B1 to B12), the matrix to Part 4, the CR register with CR-01 at Defined, CR-01 form parts 1 to 4. This session adds: C1 acceptance criteria; the matrix’s acceptance column and its two checks (blueprint 1.0); CR-01 form parts 5 to 7; decision D-13. |
| Go deeper | Test the system (the delivered build, tested role by role) · Time monitoring (when a deadline is fixed) |
◆ Orientation (1 min) — Is it done?
Section titled “◆ Orientation (1 min) — Is it done?”When Rania Saleh says “Release 1 is finished”, someone has to decide whether it does what Mariam Khalil signed. Without agreed tests, that decision becomes an argument. In this session every requirement gets its acceptance criteria, written before anything is built, and the traceability matrix you started in Part 1 gets its last column, so “is it done?” becomes a checklist. Then you put the matrix to its second use: CR-01 has waited since week 4, and the change board meets on Thursday of week 8. You size it, recommend, and record what Mariam decides.
▤ Concept (7 min) — Tests written before the build; reading a change across the matrix
Section titled “▤ Concept (7 min) — Tests written before the build; reading a change across the matrix”Acceptance criteria
Section titled “Acceptance criteria”An acceptance criterion is a result someone can check on the delivered system: it passes or it fails. Write it as Given / When / Then: given a starting situation (who is signed in, what exists), when someone acts or time passes, then an observable result, for whom and where.
Your user stories from M1-S2 say who wants what and why; the criteria say how everyone will know it works. They go in C1, under the story they prove (AC-04a, AC-04b for US-04). A requirement without a story, a quality or a Should or a Release 2 need, gets its criteria directly. For F-12:
AC-12a. Given a solved ticket, when Customer One rates it 4 with a comment, then Desk Agent sees the score and the comment, and Representative One does not.
Good criteria share five qualities:
- Observable on a screen. “Then the ticket is assigned” is weaker than “then it is listed in Hadi’s My assigned tickets”.
- Named test people. Tests are run by signing in as someone. The binder’s cast: Customer One (Lamia Fares, office manager of Cedar Dental Clinic), Customer Two (a private customer), Desk Agent (Yusuf Darwish) and a second desk member, Representative One (Hadi Nasr) and Representative Two, Support Manager (Salma Idris).
- Several per requirement when needed: the usual path, and each exception the requirement names.
- The negative case. Write what must not happen. Access is proved mostly by what people cannot see or change, and a decision by what does not happen on the other route.
- Figures for qualities. NF-04 becomes “a ticket assigned on Sunday at 09:00 and left alone is late on Tuesday at 09:00”.
Check the result, not the set-up: “then Desk Agent has a message naming the ticket”, not “a reaction exists”. Automations run in the background and fail silently; only a criterion that looks for the message proves one.
Who uses them. Mariam’s team reads the criteria as the definition of “done” and agrees them now, while changing a sentence is cheap. Rania builds to them, and checks her own work against them before she hands a release over. In the Release 1 test, Yusuf and Salma sign in as the test people and run them one by one; a failed criterion is a defect, reported with its ID. And every later change names the criteria it adds and the ones it runs again, which is why each criterion has an ID of its own and never shares one with another requirement.
The two checks
Section titled “The two checks”With the acceptance column filled, the matrix is complete: one row per requirement, from its source to its tests. Read it two ways:
- Forward: nothing forgotten. Every row has at least one design cell and at least one criterion. An empty cell is a gap to close, or a reason recorded (“withdrawn by D-03”).
- Backward: nothing unasked. Every element of B1 to B12 appears in some row. An element no requirement names is gold plating: it costs building, testing and upkeep. Take it out, or trace the person who wants it and add their need to the register. After the baseline, adding that need is a change request.
Run both checks again after every change: a change that adds an element must add the requirement it meets, and one that removes a requirement must remove its elements or find them another reason.
Reading a change across the matrix
Section titled “Reading a change across the matrix”Start at the row of the requirement the change touches and read across: every filled cell may change. Then read down each of those design columns: any other row naming the same step, field or message is touched too, although its requirement does not change, so its criteria are run again. Last, look at Changed by for earlier changes to the same rows. The cells you counted are the size of the change.
flowchart LR R["Row NF-03"] -->|"read across"| D["B8 Help Desk limit<br/>B9 desk escalations"] D -->|"read down"| O["Other rows that<br/>name the same elements"] D --> A["NF-03's own criteria"] O --> X["Their criteria:<br/>run again"]
What to notice: the change is to one requirement, but the read-down finds other rows whose tests must run again although their requirements do not change.
Step 4 of a change request: plan
Section titled “Step 4 of a change request: plan”You detected CR-01 in M1-S2, identified it in M2-S2 and defined it in M3-S3 and M4-S2. Planning fills the last three parts of the form:
| Part | What you write | Who |
|---|---|---|
| 5 Impact and size | Per option: requirements, stories, measures, process-definition sections, blueprint sections and criteria touched; the administrator’s set-up; the cost on stored records; the risk; the builder’s size | You, with the builder |
| 6 Recommendation | One option and why, in two or three sentences | You |
| 7 Decision and release | Who decided, when, which option; the version and release; the tests to write and rerun; who is told | The owner decides; you record |
The owner is the person the charter names, not the person who asked. You recommend; you never decide. The decision goes into the decisions log, and a decision that reverses an earlier one says so. Then a short communication note tells everyone affected what was decided, when it ships and what happens until then.
◇ Worked scenario (1 min) — Criteria for “each person is told”
Section titled “◇ Worked scenario (1 min) — Criteria for “each person is told””US-11: as a member of staff, I want to be told when a ticket needs me. Decide before you read on.
- How many criteria? One per hand-over that tells someone: new ticket, assignment, solution, approval. Four.
- AC-11b. Given Desk Agent sends a ticket to processing with Representative One chosen, then Representative One has a message, and Representative Two has none.
- Why the negative half? The design tells the chosen person, not the group. Only a criterion that would fail if everyone were told protects that choice.
The habit to copy: every design choice made for a reason deserves a criterion that fails if the reason is ignored.
⛏ Lab (58 min) — Criteria, the complete matrix, CR-01’s impact and recommendation
Section titled “⛏ Lab (58 min) — Criteria, the complete matrix, CR-01’s impact and recommendation”Goal. C1 for US-04, US-08, US-10 and NF-01; the matrix complete and checked both ways (blueprint 1.0); CR-01 form parts 5 and 6.
Before you start. Your stories (A9), blueprint 0.9, matrix and CR-01 form. If any of them is missing or weak, use the earlier parts’ model answers and the hand-out below.
CR-01 so far (form parts 1 to 4, in short). Mariam (J1) wants tickets of Priority accounts picked up within 2 working hours, not 4, and the account manager told when one is late; Karim Haddad (J5, merged) wants the desk to see them first. The problem: Priority clinics pay for a faster service and nobody can tell their tickets apart; about 60 tickets a month. It touches NF-03, D-05, SM-2, P1b, PDD BR-6 and section 8, B8 and B9. Option A: the Help Desk limit comes from the ticket’s Account tier (2 or 4, fallback 4), the account manager is told (new F-19), the desk gets a Priority counter (new F-18), the support manager a Priority figure (SM-5), account managers one screen and one message; Release 2 at the earliest. Option B: the desk marks urgency; it cannot shorten the desk’s own pickup, because the deadline is fixed when the ticket arrives. Option C: do nothing in the system.
What Rania Saleh says when you ask her to size the options: “A is medium, about two days inside the Release 2 build. B is small, half a day. C is nothing to build.”
Steps.
Criteria (C1)
- Write the criteria for US-04, US-08 and US-10, Given / When / Then, with IDs (AC-04a …). Cover the usual path and each exception the requirement names, with at least one negative criterion per story.
- Write at least two criteria for NF-01: one for what a person must not see, one for what a person must not change.
- File the rest of C1 from Hand-out 2 below.
The matrix (C2)
- Fill the Acceptance column for every row, from your criteria and the hand-out.
- Forward check. List every row with no design cell or no criterion. Close it, or write the reason it stays empty.
- Backward check. Go through B1 to B12. List any element no row names, and what was done with it. The blueprint is now version 1.0.
CR-01, step 4 (form parts 5 and 6)
- Read CR-01 across and down. Start at row NF-03, read across, then read down each design column it fills. Count what it touches: requirements, stories, success measures, decisions, PDD sections, blueprint sections, criteria to write and to rerun, earlier changes.
- Part 5. Write the impact and size of options A, B and C side by side: the counts, the administrator’s set-up, the cost on stored records, the risk, Rania’s size.
- Part 6. Recommend one option in two or three sentences, and say what happens until it ships. Leave CR-01 at Defined: only the board moves it.
Check.
- Every criterion names who is signed in, what they do, and what they see where.
- Each story has a criterion that would fail if a design choice were ignored.
- NF-01 has a “must not see” and a “must not change” criterion.
- Every matrix row has a criterion or a recorded reason, and the backward check is written down.
- CR-01’s rerun list includes criteria of rows other than NF-03, found by reading down.
- Part 6 recommends one option with reasons, and leaves the decision to Mariam.
Pass condition. All six boxes are ticked, your NF-01 criteria would catch Customer One seeing Customer Two’s ticket, and your part 5 shows why Option B does not meet J1.
If something goes wrong
| What you see | What to do |
|---|---|
| “Then the customer is informed” | Say where and what: which message, naming what, to whom. |
| Your NF-01 has only “she sees her own tickets” | That proves she sees something, not that she cannot see the rest. Add the negative cases. |
| US-08 has one criterion | F-08 names two outcomes: approved and refused. Each gets a criterion, and refusal must not close the ticket. |
| Your rerun list is just AC-NF03a | Read down the process column: other rows name the Help Desk step, its actions and its messages. |
| Option B looks cheaper, so you recommend it | Cost is one column. Ask which option meets both of J1’s needs. |
| You wrote “Approved” in part 7 | Part 7 belongs to the change board, in the discussion. You recommend; Mariam decides. |
Hand-out 1: the matrix at the end of Part 4 (from the reference binder)
Section titled “Hand-out 1: the matrix at the end of Part 4 (from the reference binder)”The reference matrix’s design columns, for the read-down and the forward check. “PDD” is PR-01, Ticket handling with escalation; PDD T-numbers are its steps; B9 L-numbers are the time automations (L for late).
| ID | Requirement | Data | Process and flow | People see |
|---|---|---|---|---|
| F-01 | Customer opens a ticket | B2 Ticket title, Ticket description | PDD T1; B6 tickets; B7 Open Ticket rules | B12 customers |
| F-02 | Automatic number | B2 Ticket number | PDD T1 | B11 report column 1 |
| F-03 | Customer sees where it stands | B3 Ticket status | B9 S1 to S3 | B10 Tickets I reported; B12 customers |
| F-04 | The desk claims a ticket | — | PDD T3; B7 Help Desk owner | B12 desk |
| F-05 | Duplicate, answer or pass on | B2 Assigned to; B3 Duplicate | PDD T4, T5, T7; B7 Help Desk actions | B12 desk |
| F-06 | Representative records the solution | B2 Solution | PDD T6; B7 Processing Ticket | B12 representatives |
| F-07 | The desk checks every solution | — | PDD T8, T10; B7 Help Desk; Solution hidden from the customer until sent | — |
| F-08 | Manager approves refunds, replacements | — | PDD T9; B7 Manager Approval; B9 N9 to N11 | B12 support manager |
| F-09 | Only the desk closes | — | PDD T13; B7 Close Ticket; B8 Service Evaluation; B9 L6 | — |
| F-10 | The customer is told | — | PDD T2, T11; B9 N2, N3, N7 | — |
| F-11 | Each person is told | — | B9 N1, N4 to N6, N8 to N11 | B11 counter Waiting at the desk |
| F-12 | The customer rates | B2 Service evaluation | PDD T12; B7 Service Evaluation; B8; B9 N7, L5 | B12 desk |
| F-13 | Representative sees only their own | B2 Assigned to | — | B10 My assigned tickets; B11 counter; B12 representatives; B13 DN-8 |
| F-14 | Status chart | B3 Ticket status | — | B10 Open tickets; B11 Ticket Status |
| F-15 | Monthly report by the 28th | — | — | B10 All tickets; B11 Performance Report |
| F-16 | Time from opening to closing | B2 End date, Resolution time | B9 S4 | B10 Closed tickets; B11 Average resolution time |
| F-17 | Office manager opens for staff | — | — | Withdrawn by D-03: moved to Release 2 as P4 |
| NF-01 | Each sees and changes only what their job needs | B4 (no protection needed) | PDD BR-5, C-3; B7 locked fields | B10 Tickets I reported; B12 access intent; B13 DN-9 |
| NF-02 | Everything from a phone | — | — | B12 phone column |
| NF-03 | Desk acts within 4 working hours | — | PDD BR-6, escalation; B8 Help Desk; B9 L1, L2 | B10 Waiting at the desk; B11 counter |
| NF-04 | Representative solves within 2 working days | — | PDD BR-7; B8 Processing Ticket; B9 L3, L4 | — |
| NF-05 | 400 a month and growth | B5 no long link chains | — | B10 every list opens on a saved query |
| P1a | Accounts with tier and manager | B1, B2 Customer Accounts | — | B12 desk keeps accounts |
| P1b | The ticket shows account and tier | B2 Customer account, Account tier; B5 From Parent Only | B7 Open Ticket rules | — |
| P2a | Customer requests a visit | B2 Site Visit Requests; B5 Related ticket | B6 visit card; B7 Request visit | B12 customers |
| P2b | Manager approves each visit | B3 Visit status; B5 Account tier, Never | B7 Manager approval; B9 V1, V3 to V5 | B10 Visits waiting for approval; B12 support manager |
| P2c | Engineers take, date, record | B2 Field engineer, Visit date, Visit outcome | B7 Schedule and visit; B9 V2, V6, V8 | B10 My visits; B11 counter; B12 engineers |
| P2d | Customer confirms the visit | — | B7 Customer confirmation; B8; B9 V7, V9, V10 | — |
| P3a | Public pre-sales form | B2 Pre-sales Questions | B6 pre-sales card; B7 pre-sales; B9 Q1, Q2 | B10 Open questions; B12 visitors, desk |
| P3b | Keep spam out | — | B6 Human Verification; risks R-5, R-6 | B12 visitors |
| P4 | Office managers act for staff | B2 Reported for, Contacts | B6 on behalf of; B9 N12 | B10 My account’s tickets; B12 office managers |
| P5 | Quality officer follows visits | — | B6 watchers, group Quality | B12 quality officer |
| P6 | One list of open work | B5 Aggregate Entity All open work | — | B12 support manager |
Hand-out 2: the rest of C1 (from the reference binder)
Section titled “Hand-out 2: the rest of C1 (from the reference binder)”File these under C1. They complete the criteria you wrote; US-11’s are the worked scenario’s.
Stories
- AC-01a. Given Customer One is signed in, when she opens a ticket with a title and a description and sends it, then it is listed among her tickets with both texts as she wrote them.
- AC-01b. Given Customer One is filling in a ticket, when she leaves the title empty and tries to send it, then it is not sent and the title is marked as needed.
- AC-02a. Given Customer One and Customer Two each send a ticket within the same minute, then each ticket shows a different number, and neither of them typed it.
- AC-03a. Given three tickets opened by Customer One at different steps, when she opens her tickets on the web and on a phone, then each shows its number and status, and opening one shows the step it is at.
- AC-05a. Given a ticket at the desk that repeats an open one, when Desk Agent sets it to Duplicate and closes it, then its status is Closed after Duplicate, and Customer One is not told it is solved.
- AC-05b. Given a ticket at the desk with no representative chosen, when Desk Agent looks for the way to send it to processing, then it is not offered until he chooses one.
- AC-05c. Given a ticket at the desk, when Desk Agent writes the solution himself and sends it, then it reaches Customer One without passing a representative.
- AC-06a. Given a ticket assigned to Representative One, when he sends it back without a solution, then it does not move on; when he writes one and sends it, it is back at the desk with the solution.
- AC-07a. Given Representative One has sent back a solution, when Customer One opens her ticket, then she does not see the solution until Desk Agent has sent it.
- AC-11a. Given a new ticket is sent, then every member of the desk has a message naming its number.
- AC-11b. Given Desk Agent sends a ticket to processing with Representative One chosen, then Representative One has a message, and Representative Two has none.
- AC-11c. Given Representative One sends back a solution, then the desk is told there is a solution to review; given Desk Agent sends it, then Representative One is told.
- AC-11d. Given Desk Agent sends a ticket for approval, then Support Manager is told; given she decides, then the desk is told which way she decided.
- AC-14a. Given tickets in every status, when Support Manager opens the desk’s list, then the status chart shows one figure per status, and selecting a part of it lists exactly those tickets.
- AC-14b. Given she opens the same chart on a phone, then it shows the same figures.
Release 1 requirements without a story
- AC-09a (F-09). Given a ticket at Service Evaluation, when Customer One has rated it, then she has no way to close it; it returns to the desk, which closes it.
- AC-12a (F-12). As in the concept above.
- AC-13a (F-13). Given open tickets assigned to Representative One and to Representative Two, when Representative One opens his tickets, then only his open tickets are listed, and the counter shows their number.
- AC-15a (F-15). Given the 28th of the month at 08:00, then Support Manager has an email with the report as a PDF, listing every ticket with its number, title, status, handler and dates; and the report also opens on the web.
- AC-16a (F-16). Given tickets closed last month, when Support Manager opens the resolution chart, then it shows the average time from opening to closing for that month.
- AC-NF02a (NF-02). Given Customer One on a phone, when she opens a ticket, follows it and rates it, then every step works in the app.
- AC-NF03a (NF-03). Given Office hours and a public holiday on Sunday, when a ticket reaches the desk on Thursday at 14:30 and nobody acts on it, then it turns overdue on Monday at 10:30 and the desk is told; 2 working hours later Support Manager is told. (Test with a limit of a few minutes, then restore the real one.)
- AC-NF04a (NF-04). Given a ticket assigned to Representative One on Sunday at 09:00, when he does nothing, then on Tuesday at 09:00 he is told it is late, and 4 working hours later, at 13:00, the desk is told.
- AC-NF05a (NF-05). Given 5,000 tickets in the system, when Desk Agent opens the desk’s list and filters it by status, then the list appears in under 3 seconds. (Target figure to be confirmed with Rania Saleh; recorded as the builder’s test.)
Release 2
- AC-P1a-a (P1a). Given the account Cedar Dental Clinic with tier Priority and account manager Karim Haddad, when Desk Agent opens it, then he sees the tier, the manager, and the account’s tickets.
- AC-P1b-a (P1b). Given Customer One is a contact of Cedar Dental Clinic, when she opens a ticket and picks the account, then the ticket shows Cedar Dental Clinic and Priority; she is not offered any account she is not a contact of.
- AC-P1b-b (P1b). Given an open ticket of Cedar Dental Clinic, when the account’s tier is changed to Standard, then the open ticket shows Standard (D-07).
- AC-P2a-a (P2a). Given Customer One has two tickets, when she requests a site visit, then she can pick only her own tickets, and the request is in her Outbox.
- AC-P2b-a (P2b). Given a visit request, when Support Manager chooses Not approved, then she must write a comment, the customer is told, and the request ends.
- AC-P2c-a (P2c). Given an approved visit, when a field engineer claims it, then he cannot send it on without a visit date and an outcome; and it appears on his calendar.
- AC-P2d-a (P2d). Given a visit marked done, when Customer One says it did not take place, then she must write a comment and the visit returns to the field engineers.
- AC-P3a-a (P3a). Given a visitor who is not signed in, when they fill in the pre-sales form and pass the check, then the question reaches the desk, and the answer is emailed to the address they gave.
- AC-P3b-a (P3b). Given the public form, when someone tries to send it without completing the “I’m not a robot” check, then it is not sent; a signed-in customer is never shown the check.
- AC-P4-a (P4). Given Customer One opens a ticket reported for her receptionist, then the receptionist is told about it and can follow it; and Customer One sees it among her account’s tickets.
- AC-P5-a (P5). Given any visit request, when Ziad Amin opens Watching, then he sees it at every step and has no action on it.
- AC-P6-a (P6). Given 3 open tickets and 2 open visits, when Support Manager opens All open work, then she sees 5 rows, and opening one takes her to the ticket or the visit to act there.
Model answer
Your criteria (C1)
- AC-04a. Given a new ticket at the desk and two desk members signed in, when Desk Agent claims it, then it is his, and the second desk member can no longer claim it.
- AC-04b. Given a ticket Desk Agent claimed has gone to a representative and come back, then it returns to Desk Agent, not to the whole desk.
- AC-08a. Given a ticket at the desk with a proposed replacement, when Desk Agent sends it for approval, then it appears in Support Manager’s work and Desk Agent has no action on it until she decides.
- AC-08b. Given that ticket at the manager, when Support Manager refuses it, then she must write a comment, and the ticket is back with Desk Agent, not closed.
- AC-10a. Given Customer One sends a ticket, then within a minute she has a message saying it is received, with its number.
- AC-10b. Given her ticket is sent to Representative One, then she has a message saying someone is working on it.
- AC-10c. Given Desk Agent sends the solution, then she is told it is solved and asked to rate; and when Desk Agent instead closes a duplicate, she is not told it is solved.
- AC-NF01a. Given a ticket opened by Customer Two, when Customer One searches for its number, then nothing is found.
- AC-NF01b. Given a ticket at Processing Ticket, when Representative One opens it, then he cannot change its title or description, and he does not see the service evaluation.
Your wording can differ. A criterion passes if a tester could run it by signing in as the people it names, and it would fail if the design choice behind it were ignored (AC-04b: the ticket comes back to its owner; AC-10c: the “solved” message belongs to sending the solution, not to leaving the desk).
The acceptance column (C2)
| Row | Acceptance | Row | Acceptance |
|---|---|---|---|
| F-01 | AC-01a, AC-01b | NF-01 | AC-NF01a, AC-NF01b |
| F-02 | AC-02a | NF-02 | AC-NF02a, AC-14b |
| F-03 | AC-03a | NF-03 | AC-NF03a |
| F-04 | AC-04a, AC-04b | NF-04 | AC-NF04a |
| F-05 | AC-05a to AC-05c | NF-05 | AC-NF05a |
| F-06 | AC-06a | P1a | AC-P1a-a |
| F-07 | AC-07a | P1b | AC-P1b-a, AC-P1b-b |
| F-08 | AC-08a, AC-08b | P2a to P2d | AC-P2a-a, AC-P2b-a, AC-P2c-a, AC-P2d-a |
| F-09 | AC-09a | P3a, P3b | AC-P3a-a, AC-P3b-a |
| F-10 | AC-10a to AC-10c | P4 | AC-P4-a |
| F-11 | AC-11a to AC-11d | P5 | AC-P5-a |
| F-12 to F-16 | AC-12a, AC-13a, AC-14a and AC-14b, AC-15a, AC-16a | P6 | AC-P6-a |
| F-17 | Withdrawn: tested as P4 |
Forward check. No unexplained gap. Two recorded exceptions: F-17 (withdrawn by D-03, its need tested as P4), and the empty Data cells of rows that need no data of their own (F-04, F-07 to F-11, P2d, P3b, P5), whose design is in the next column.
Backward check. Every element of B1 to B12 names a requirement. Two failed the check earlier and were dealt with: the pilot’s typed Start date (removed in M2-S1, DN-1) and a visit report document proposed in M4-S1 (not specified; logged as a next-phase idea).
Reading CR-01 across and down
| What CR-01 touches | Count | Which |
|---|---|---|
| Requirements | 2 changed or reused, 2 new | NF-03 changed; P1b (its tier now sets a limit); F-18, F-19 new |
| User stories | 0 | Stories cover the Release 1 Musts; CR-01 is a Release 2 change |
| Success measures | 1 new | SM-5 |
| Decisions | 1 superseded | D-05 (no urgency in Release 1) |
| PDD sections | 5 | 4 roles, 6 (T3 via BR-6), 7 BR-6, 8 escalation, 9 measures |
| Blueprint sections | 8 | B2 (two fields), B5 (one mapped field), B7 (two field-rule rows), B8 (Help Desk method), B9 (two automations), B10 (three queries), B11 (one figure, one counter), B12 (one audience, one hand-off line) |
| Criteria | 7 new, 7 rerun | New: AC-NF03b, AC-NF03c, AC-NF03d, AC-18a, AC-18b, AC-19a, AC-SM5a. Rerun: AC-04a, AC-05a, AC-10a, AC-11a, AC-NF03a, AC-P1b-a, AC-P1b-b |
| Earlier changes | 0 | No “Changed by” entry before CR-01 |
Part 5 — Impact and size
| Option A | Option B | Option C | |
|---|---|---|---|
| Requirements | NF-03 changed; F-18, F-19 new; P1b reused | NF-04 changed (the representative’s limit only); one new | 0 |
| User stories | 0 (Release 2) | 0 | 0 |
| Success measures | SM-5 new | — | — |
| PDD sections | 5 (4, 6, 7, 8, 9) | 3 (6, 7, 8) | 0 |
| Blueprint sections | 8 (B2, B5, B7 to B12) | 4 (B2, B7, B8, B9) | 0 |
| Criteria | 7 new, 7 rerun | 3 new, 4 rerun | 0 |
| Administrator | An optional group Account Managers | None | None |
| Cost on stored records | Optional fields and a mapped field: safe. The step’s limit changes its method; no step is added, removed or moved | One optional field: safe | — |
| Risk | A Priority contact who leaves the account empty gets 4 hours (made visible by a criterion); the 2-hour limit also applies when a solution returns to the desk (D-11) | Every ticket gets marked urgent; does not meet J1 | Complaints continue; no evidence for the contract |
| Builder’s size | Medium: about 2 days, in the Release 2 build | Small: about half a day | — |
Part 6 — Recommendation. Option A. It is the only option that sets the 2-hour limit at the moment the ticket arrives, tells the account manager, and lets the business measure the promise (SM-5). It costs about two days inside the Release 2 build, adds no workflow step, and changes nothing for Standard tickets. Until Release 2, use Option C as an interim: the desk looks at Priority clinics first by name.
✳ Discussion (10 min) — The change board
Section titled “✳ Discussion (10 min) — The change board”Thursday of week 8. Mariam Khalil chairs the change board; Salma Idris, Yusuf Darwish and Rania Saleh attend. You present CR-01, and part 7 of the form is written in the room.
With a facilitator. The facilitator plays Mariam. In groups, agree which option you will ask for and the one sentence that argues it (3 min). Each group presents in one minute; “Mariam” asks questions and decides, giving her reason (4 min). Everyone then writes part 7, decision D-13 and the communication note, and moves CR-01 to Decided in the register (3 min).
On your own. First write, in three sentences, the decision you would ask Mariam for (2 min). Then read the board’s outcome below, and write part 7, D-13 and the communication note (5 min).
The board’s outcome. Mariam approves Option A for Release 2 (week 18), with Option C as the interim until then. Her reason: “Only A keeps the promise we sell, and lets me see whether we keep it.” Rania confirms the two days fit the Release 2 build.
Model answer
Part 7 — Decision and release
| Decided by | Mariam Khalil, at the change board, Thursday week 8. Present: Salma Idris, Yusuf Darwish, Rania Saleh; the analyst presented. |
| Decision | Option A approved, for Release 2 (week 18). Option C as the interim until then. Recorded as D-13. |
| Documents | BRD 1.1 (A0, A3, A4, A5, A8, A10, A11, C3, C4); PDD 1.1 (approved by Salma Idris); blueprint 1.1; matrix rows NF-03, P1b, F-18, F-19 |
| Tests | Write AC-NF03b, AC-NF03c, AC-NF03d, AC-18a, AC-18b, AC-19a, AC-SM5a; rerun AC-04a, AC-05a, AC-10a, AC-11a, AC-NF03a, AC-P1b-a, AC-P1b-b in the Release 2 test |
| Who is told | Mariam Khalil and Karim Haddad (requesters); the desk, through Yusuf Darwish (the interim rule now, the new counter and limit in Release 2); Rania Saleh (build); Tariq Mansour (the group); account managers (their new screen and message, at Release 2 training) |
D-13 (A11). CR-01 approved, Option A, for Release 2. D-05 is superseded for Priority accounts. Decided by Mariam Khalil at the change board (Salma Idris, Yusuf Darwish, Rania Saleh), Thursday week 8. Changes: BRD 1.1, blueprint 1.1, PDD 1.1, the matrix; see the CR-01 form, part 7.
The register line. CR-01: status Decided; decision “Approved, Option A, for Release 2 (D-13) · Mariam Khalil · Thursday week 8”.
The communication note (sent the same day to the people above)
CR-01 “Priority accounts are answered faster” was approved today by Mariam Khalil. From Release 2 (week 18), tickets of Priority accounts must be picked up within 2 working hours, and the account manager is told when one is late; the desk will see a count of Priority tickets waiting, and account managers will see their accounts’ open tickets. Until then, the desk looks at Priority clinics first by name. The BRD, the process definition and the blueprint will be issued as version 1.1 next week. Nothing changes for other tickets.
A good note says what was decided, when it ships, what happens until then, and what does not change. It never makes the analyst the decider.
✓ Practice (6 min) — Check your understanding
Section titled “✓ Practice (6 min) — Check your understanding”F-08 says that whatever the support manager decides, the ticket returns to the desk. Which criterion would fail if a builder closed refused tickets instead?
Check your answer
The correct answer is B. Open the explanation under each option to see why.
In the forward check, row P5 (the quality officer follows every visit) has an empty Data cell, but its process and “people see” cells are filled, and it has a criterion. What does the empty cell show?
Check your answer
The correct answer is A. Open the explanation under each option to see why.
CR-01 changes the Help Desk step’s time limit and its messages. Reading down the matrix’s process column, whose criteria do you run again? Select all that apply.
Check your answer
The correct answers are A and B. Open the explanation under each option to see why.
Who decides CR-01 at the change board, and why that person?
Check your answer
The correct answer is C. Open the explanation under each option to see why.
Put step 4 of a change request in order.
Check your answer
The correct order is D → A → C → E → B. Open the explanation under each item to see why it sits where it does.
↺ Recap (1 min) — Your binder now: blueprint 1.0, traced
Section titled “↺ Recap (1 min) — Your binder now: blueprint 1.0, traced”After Module 5 you can write acceptance criteria a tester can run by signing in as a named person, including what must not happen; keep a traceability matrix that finds gaps in both directions; and take a change request through its last step, from the read-across to the communication note.
Your binder now (Part 5). Tick each line, then compare with this session’s model answers and hand-outs.
- Blueprint 1.0: every requirement traced forward to design and criteria; every element traced back to a requirement.
- C1 complete: your criteria for US-04, US-08, US-10 and NF-01, and the hand-out’s for the rest.
- Criteria name who is signed in and what they see; access has negative criteria.
- The matrix’s acceptance column is filled, and both checks are written down.
- CR-01 decided: form parts 5 to 7, D-13 in the decisions log, the register at Decided, the communication note sent.
Next. In M6-S1 you do what the communication note promised: you put CR-01 into every document, and the BRD becomes version 1.1.