The traceability matrix is one table with one row per requirement. Reading a row left to right tells you where the requirement came from, where the design meets it, and how you will prove it works. Reading a column top to bottom tells you whether anything was forgotten, or added without being asked for.

You start it in Module 1 and add one group of columns per module. By Module 5 it is complete. From then on you use it every time something changes.

ColumnsWhat goes in themFilled in
ID · Requirement · PriorityFrom the requirements registerM1-S2
SourceThe person, document or observation it came fromM1-S2
User storyThe story ID, for the Must requirementsM1-S2
DataThe entity, field or status value it needs (blueprint B1–B5)M2-S1, M2-S2
Process and flowThe process step or business rule that meets it (the process definition, or the future-process map), then the service card, workflow step, field rule, time limit or notification (B6–B9)M3-S1 to M3-S3
What people seeThe query, figure, report, screen or audience row that meets it (B10–B12)M4-S1, M4-S2
AcceptanceThe acceptance-criteria IDs that prove it (C1)M5-S1
Changed byThe CR numbers that altered the row, or that now rely on one of its design elements, newest lastFrom the first change

Write blueprint references as section and row (for example B7 step 3), not page numbers: pages move, section numbers do not.

Forward: nothing forgotten. Every requirement row has at least one entry in the design columns and at least one acceptance criterion. An empty cell is either a gap to close or a decision to record (“met by a manual step, outside the system”).

Backward: nothing unasked. Every element of the blueprint appears in at least one row. A field, step or report that meets no requirement either answers a need you forgot to write down (add the requirement and its source) or should not be built (remove it).

When a change request arrives, find the row of the requirement it changes and read across: every filled cell is something the change may touch. Then read down each of those design columns: any other row that names the same step, field, rule or report is touched too, even though its requirement did not change, and its criteria must be run again. Then search the “Changed by” column for earlier changes to the same rows. The count of touched cells is the size of the change you put on the CR form.

  • One row per requirement, in the register’s order and with the register’s IDs.
  • No empty design or acceptance cell without a recorded reason.
  • Every blueprint element appears in at least one row.
  • References are section and row, not page numbers.
  • Every approved change request is listed on the rows it changed.