Job aid: the BRD and blueprint template
Section titled “Job aid: the BRD and blueprint template”The structure of the document you build up during this course: one binder, three parts. Each section says in which part of the course you write it and in which version of the binder it first appears. Copy the headings into your own document and keep the section numbers, because the traceability matrix refers to them.
Each document keeps its own version number.
| Document | Versions | What they mean |
|---|---|---|
| BRD (Part A) | 0.1 in Part 0 · 1.0 at the end of Part 1 · 1.1 in Part 6 | 0.1: the binder is open. 1.0: signed by the sponsor; this is the baseline, and from now on anything that would change it is a change request. 1.1: the first approved change request is in. |
| Process definition (a sub-document of A6 and A7) | 0.1 in Part 1 · 1.0 in Part 3 · 1.1 in Part 6 | 0.1: the process as it runs today. 1.0: the future process, its rules, exceptions, escalation and controls, approved by the process owner. 1.1: the change request’s effects. |
| Blueprint (Part B) | 0.3 in Part 2 · 0.6 in Part 3 · 0.9 in Part 4 · 1.0 in Part 5 · 1.1 in Part 6 | It grows section by section; 1.0 when acceptance is complete and every requirement is traced. |
Work done after the baseline that adds detail without contradicting the BRD (the blueprint, the future process, the answer to a question the BRD left open) is elaboration, not change. Anything that makes the system do something the BRD does not say, or say it differently, is a change request.
Part A: Business Requirements Document
Section titled “Part A: Business Requirements Document”The business’s words only. No option names, no field types.
| No. | Section | What it holds | Written in | Version |
|---|---|---|---|---|
| A0 | Document control | Title, version, date, author, reviewers, approvals with dates, change log, the list of sub-documents | Part 0 | 0.1 |
| A1 | Business need | The problem today, who has it, what it costs; the decision asked of the reader | Part 0 | 0.1 |
| A2 | Summary | The need and the solution in two sentences; written last, kept short | Part 6 | 1.1 |
| A3 | Objectives and success measures | Measurable objectives: what changes, for whom, by how much, checked how; missing figures as open questions | M1-S1 | 1.0 |
| A4 | Scope | In scope, out of scope, later (phases); assumptions and constraints; every “not available” with its workaround | M1-S1 | 1.0 |
| A5 | Stakeholders and users | Who uses, runs, pays for and is affected by the system; what each needs; who approves what | M1-S1, M1-S2 | 1.0 |
| A6 | Current process | The process as it runs today, in short, with each pain point and the requirement that removes it; the map is in the process definition (version 0.1) | M1-S2 | 1.0 |
| A7 | Future process | At 1.0: how the business will work, in a few numbered sentences. From Part 3: the to-be maps, in the process definition (largest process) and here (the others) | M1-S2, then M3-S2 | 1.0, detailed later |
| A8 | Requirements register | ID · requirement · functional or not · source · priority · reason | M1-S2 | 1.0 |
| A9 | User stories | For the Release 1 Must requirements that a person does: “As a … I want … so that …”; a story takes its requirement’s number; acceptance criteria are added in C1 | M1-S2 | 1.0 |
| A10 | Risks | What could stop the system meeting its objectives | M1-S2, M3-S1 | 1.0 |
| A11 | Open questions and decisions | Each question with the person who answers it and the answer once given; each decision with who made it and when | M1-S2 onward | 1.0 |
Sub-documents of the BRD
Section titled “Sub-documents of the BRD”| Sub-document | What it holds | Written in |
|---|---|---|
| Process definition (one per large process) | Purpose and scope; the process at a glance; roles; the current process (map and steps); the future process (map and steps, each naming its requirement and the workflow step that carries it); business rules; exceptions and escalation; measures; controls; open points; change history | Current process in Part 1; the rest in Part 3 |
| Process maps | Swimlane maps: a lane per role; start and end; task; decision; hand-off; wait | Parts 1 and 3 |
| Traceability matrix (C2) | See the traceability job aid | From Part 1 |
| Change-request register and forms (C3) | See the change-request job aid | From Part 1 |
Part B: Solution blueprint
Section titled “Part B: Solution blueprint”The platform’s words. Every row names the requirement IDs it meets.
| No. | Section | What it holds | Written in |
|---|---|---|---|
| B1 | Module and entities | Which module; the entity list; why each is an entity | M2-S1 |
| B2 | Entity dictionaries | Per entity: field · type · required · default · filled in by · requirement · note; main and sub title | M2-S1 |
| B3 | Status models | Per status field: value · meaning · set by · when | M2-S1 |
| B4 | Protection | Sensitive or Encrypt, who may see, and the cost | M2-S1 |
| B5 | Links | Map; relations table; mapped fields with Update Mode and reason; virtual entities | M2-S2 |
| B6 | Front doors | Service cards; which requests use a view’s form, and why | M3-S1 |
| B7 | Workflows | Steps; owners and fallbacks; actions and targets; field-rules matrix; status sync | M3-S2 |
| B8 | Time limits | SLA policy; escalation; what the administrator sets up | M3-S3 |
| B9 | Notifications and automation | Matrix: no. · name · event · recipients · channel · message · requirement | M3-S3 |
| B10 | Queries | Catalog: name · entity · conditions · used by · requirement | M4-S1 |
| B11 | Figures, counters, reports, documents | Summaries; counters; reports with schedule; templates; limits noted | M4-S1 |
| B12 | Audiences and access intent | Per audience: screens, figures, phone, access intent; hand-off list for the administrator | M4-S2 |
| B13 | Design notes | Decisions the builder must not change without asking; improvements to what exists | M2-S1 onward |
Part C: Acceptance and change
Section titled “Part C: Acceptance and change”| No. | Section | What it holds | Written in |
|---|---|---|---|
| C1 | Acceptance criteria | Per story, and per requirement that has no story: Given / When / Then, named people, negative cases | M5-S1 |
| C2 | Traceability matrix | One row per requirement, one column group per part; see the traceability job aid | Started M1-S2, complete M5-S1 |
| C3 | Change requests | The CR register and one form per CR; see the change-request job aid | From M1-S2 |
| C4 | Change log | Per version: which CRs it carries, which sections changed, which criteria were rerun | M6-S1 |