Job aid: change requests
Section titled “Job aid: change requests”Once the sponsor signs the BRD, it is the baseline: the agreed answer to “what are we building?”. From that moment, anything that would make the system do something different from the baseline is a change, whoever asks for it and however small it sounds. A change is not bad news. A change that nobody wrote down is. This job aid gives you the four steps, the register and the form.
The four steps
Section titled “The four steps”| Step | The question you answer | What you write | Taught in |
|---|---|---|---|
| 1. Detect | Is there a change hidden in this message, meeting or remark? | A line in the CR register, or a note saying why it is not a change | M1-S2 |
| 2. Identify | What kind of change is it, who owns it, and what in the baseline does it touch? | The register line completed: type, requester, source, affected IDs | M2-S2 |
| 3. Define | What exactly would change, and what are the ways to do it? | The CR form, parts 1 to 4 | M3-S3, M4-S2 |
| 4. Plan | What does it cost, what do we recommend, who decides, and when does it ship? | The CR form, parts 5 to 7, and the decision record | M5-S1 |
Then the approved change goes into the documents: a new version of the BRD and the blueprint, the change log, and the traceability matrix (M6-S1).
Step 1: detect
Section titled “Step 1: detect”Changes rarely arrive labelled. Look for them in emails, meeting notes, support calls, a comment on a screen during a demo, a “while you’re at it”. Read every new message against the baseline and ask:
- Does it ask the system to do something the baseline does not say?
- Does it ask for something the baseline says, but differently: faster, for other people, in another order?
- Does it remove or loosen something the baseline requires?
- Does it reverse a decision recorded in the baseline? A decision is part of the baseline just like a requirement, even when no requirement’s words change.
If the answer to all four is no, it is not a change. Say what it is instead:
| It is | Because | What you do |
|---|---|---|
| A clarification | The baseline already covers it; the message explains or confirms how | Add the answer to the open-questions log; no version change |
| A defect | The baseline says it, and the delivered system does not do it | Report it to the builder with the requirement ID; no CR |
| A next-phase idea | It is new, and the sender agrees it can wait | Add it to the later list in the scope section; no CR now |
| A change | New, different or removed, and wanted in this release | Log it in the CR register |
When you are not sure, log it. A CR can be closed as “not a change” in one line. A missed change turns up later as a dispute.
Two messages, one change. A change request is about a need, not about a sender. When a second message asks for what an open CR already covers, add it to that CR as a second source (and any detail it adds) instead of opening another: one need is decided once, designed once and tested once.
Step 2: identify
Section titled “Step 2: identify”Complete the register line:
- Type: new requirement, changed requirement, removed requirement.
- Requester and source: the person, and the message or meeting it came from, with its date.
- Affected IDs: every requirement, user story, decision, process step or rule, blueprint section and acceptance criterion it touches. Start from the requirement it changes, then follow the traceability matrix to everything that row reaches, including the process definition: a change to a step can touch a rule or a control the business relies on.
- Owner: the person who decides it, as the project charter says. The person who asks is often not the person who decides, even when they own the process.
Step 3: define
Section titled “Step 3: define”Write the request as received, then the problem behind it: people ask for a solution (“add a field”) when they have a need (“we cannot tell urgent tickets apart”). Then write at least two options, including “do nothing”, each with what it changes in the documents.
Step 4: plan
Section titled “Step 4: plan”Size each option by counting what it touches in the traceability matrix: requirements, stories, blueprint sections and acceptance tests. Recommend one option and say why. The decision belongs to the owner, not to you; record it with the date. Then plan the release: which version it goes into, which tests are rerun, and who must be told.
The CR register
Section titled “The CR register”One row per change request, kept as an appendix of the BRD.
| CR | Date | Requester · source | Summary | Type | Affected IDs | Status | Decision · date | Version |
|---|---|---|---|---|---|---|---|---|
| CR-01 | Logged |
Status moves through Logged → Identified → Defined → Decided → Done, or ends at Closed: not a change. A rejected CR stays in the register with its reason; it is part of the record.
The CR form
Section titled “The CR form”One page per change request.
| Part | Heading | What it holds |
|---|---|---|
| 1 | The request as received | The requester’s words, quoted, with the source and date |
| 2 | The problem behind it | The need, in the business’s words; how often it happens and what it costs today |
| 3 | What it touches | The affected IDs from the register, and the baseline text each one changes |
| 4 | Options | At least two, including “do nothing”: what each changes in the BRD, the process definition (its rules and controls) and the blueprint |
| 5 | Impact and size | Per option: the count of requirements, stories, blueprint sections and tests touched; what the administrator must set up; the cost on stored records; the risk |
| 6 | Recommendation | The option you recommend and why, in two or three sentences |
| 7 | Decision and release | Who decided, when, which option; the version it ships in; the tests to rerun; who is told |
Check yourself
Section titled “Check yourself”- Every message after the baseline was read, and each one was logged or answered as a clarification, a defect or a next-phase idea.
- Every CR names a requester, a source and a date.
- The affected IDs came from the traceability matrix, not from memory.
- Every CR form has at least two options, one of them “do nothing”.
- The decision is recorded with its date and the decider’s name, and it is not yours.
- An approved CR changed the version number, the change log and the matrix.