After this session you canSay what goes into each document of the binder, recognise each building block of a delivered system, and write the objectives, scope, platform fit and stakeholders of a BRD.
TimeFacilitated: 65 min · On your own: 65 min
Before you startM0-S1: your binder at version 0.1, and the prework passed, with yourself and Customer One signed in, in two windows. The case file open.
Your binderBefore: BRD 0.1 (A0, A1). This session adds: A3 objectives and success measures, A4 scope and platform fit, A5 stakeholders.
Go deeperUnderstand the business need · Building blocks

◆ Orientation (1 min) — Four people, one lost ticket

Section titled “◆ Orientation (1 min) — Four people, one lost ticket”

Read the observation log in the case file. In one morning, two people answered the same email, one ticket was never written down, one waited two days for a person on leave, and the manager’s “how many are open?” took a hand count.

Nobody there lacked effort. What was missing was a system: one place where each problem is a record with a number, a status and an owner. Your job is to describe that system so exactly that a builder can make it without asking what you meant. Today you say what success looks like, what is in and out, and who the system is for.

▤ Concept (8 min) — Two documents, sub-documents, measurable objectives, platform fit

Section titled “▤ Concept (8 min) — Two documents, sub-documents, measurable objectives, platform fit”

In ACP you broke a process down with five questions: need, data, people, automation, reporting (ACP M1-S1). On a real project the answers grow into two documents, written for two different readers.

The Business Requirements Document (BRD) is written for the business. It uses their words and never names a platform option. It holds the problem and the objectives, the scope, the stakeholders, the current and future process, the requirements (one numbered, testable statement per need), the user stories, the risks, and the open questions and decisions.

The solution blueprint is written for the builder. It says how the platform meets each requirement, with the builder’s own option names: the entities and their fields, how requests come in, the workflow with its owners and time limits, the messages, the figures and reports, and, for each audience, the access intent: who must see, do and be told what.

Three sub-documents hang off the BRD. The process definition describes the largest process step by step, with its swimlane maps, rules and escalation. The traceability matrix gives every requirement one row and shows where it came from, where the design meets it and which test proves it. The change-request register records every request to change the BRD once it is signed.

flowchart LR
  S["Stakeholders<br/>interviews, emails, observation"] --> B["BRD<br/>numbered requirements"]
  B --- P["Process definition<br/>maps, steps, rules"]
  B --> L["Solution blueprint<br/>the platform's building blocks"]
  L --> D["Builder"]
  M["Traceability matrix<br/>one row per requirement"] -. "source, design, test" .- B
  M -.- L
  C["Change-request register"] -. "after sign-off" .- B

What to notice: the BRD never names an option and the blueprint never invents a need; the matrix is the thread that lets anyone check one against the other.

Design depth: name the option, never the click

Section titled “Design depth: name the option, never the click”

You never build in this course, but you must know what the builder can choose, or your blueprint will be vague (“route it to the right person”) or impossible. You name the option: “any desk member can claim a new ticket” becomes Help Desk step, owner Group Technical Support Office, Single User, Take Ownership. You give the reason: “not First one, because desk members go on leave” (case file B). You leave the mechanics to the builder: click-paths, the order of building, and any formula. Where a rule needs one, you state it in words and write “the builder writes the formula”.

In ACP you met the gains digital transformation brings: visibility, speed, quality and less paper (ACP M1-S1). In a BRD a gain becomes an objective: what changes, for whom. A success measure is how the business will check it from the system after go-live: what is counted, against which target, how often. The target belongs to the sponsor. Here the charter already sets four measures, SM-1 to SM-4; each objective you write points to one of them. If a need has no figure, you never invent one: you write the objective and leave the figure as an open question for the sponsor.

A wishAn objectiveIts success measure
“Faster support”New tickets are picked up quickly and predictably.Nine in ten new tickets picked up within 4 working hours, from the tickets’ own records.
“Management visibility”The support manager sees how support performs without counting.The monthly report arrives by the 28th, every month.
“Better service”No request is lost.Of 20 emails and calls sampled each month, every one has a ticket number.

Scope says what this project delivers and what it does not. In scope lists what each release delivers. Out of scope repeats what the charter excludes, so nobody assumes it. Later holds what someone wants and everyone agrees can wait: writing it down is what stops it returning as a surprise. Assumptions and constraints (working hours, no new staff) sit beside it.

List every group that uses, runs, pays for or is affected by the system, what it needs, and what it approves. A group you leave out is a set of requirements you will miss.

StakeholderRole in the systemMain needApproves
CustomersOpen tickets, follow them, rate the serviceA number, news, a phone that works—
The desk (Technical Support Office)Receive, route, check, closeOne queue, no duplicates, control of every answerEvery solution before the customer sees it
RepresentativesSolveOnly their own tickets, and a place for the solution—
Support managerApproves costly solutions; reads figuresApprove only what costs money; monthly figuresRefunds and replacements; the process definition
Customer Service DirectorSponsorFigures on speed; a system that growsThe BRD and every change to it

Before you promise anything, sort each need into one of three groups.

  • Ready-made. It works as soon as the building block exists; nobody configures it. The mobile app shows the same views as the web. Each person switches the portal between Arabic and English. If two people act on the same record at the same moment, only the first action counts and the second is told the record changed.
  • Configure. A builder sets it up from the platform’s options, without code: a running number, a route through several people, a notification, a chart, a scheduled report, a time limit that skips weekends.
  • Not available. You say so, with a workaround (another way to meet the real need) or a scope note. There are no points, badges or game features; there is no HR profile of a person’s skills; reports open on the web only, not in the mobile app; a report exports to PDF or Excel, and CSV comes only from a list’s own Export Entries.

▶ Guided demo (11 min) — Tour the pilot as its users (six stops)

Section titled “▶ Guided demo (11 min) — Tour the pilot as its users (six stops)”

With a facilitator. Follow each stop in your own windows while the facilitator does it on the shared screen; at each Notice, name the building block before reading on. On your own. Do the same; the screenshots show what to expect.

Look; do not act. After each stop, name the building block in ACP’s words.

As the customer (Customer One, in your private window)

  1. Open Customer Support System › Ticket Request. Notice: a view on the Support Tickets entity, showing its entries in the Table view face.
  2. Open any ticket that is not closed. It opens with its fields and, at the side, its workflow. Notice: the record is an entry; the side panel shows the workflow: the step it is at and who owns it.

Screenshot pending A ticket opened as Customer One, its fields on the left and the workflow panel on the right showing the current step Help Desk What to notice: the customer sees where the ticket is (the step) even though they cannot act on it.

  1. Look at the bell at the top. Notice: this is where notifications arrive; a reaction sent each one.

As the desk (Desk Agent). In the private window, open the profile menu, sign out, and sign in as Desk Agent.

  1. Open Customer Support System › Incoming Requests. It opens on a doughnut chart. Notice: a summary (Ticket Status) on the view’s dashboard, which opens first.
  2. Select the In Progress segment of the chart. The tickets behind it are listed. Notice: the chart is built from the same entries; one click takes the desk from the figure to the work.

Screenshot pending Incoming Requests open as Desk Agent, landing on the Ticket Status doughnut chart with segments for each status What to notice: the desk’s view and the customer’s view show the same entity in different ways, for different people.

  1. Open a ticket at the Help Desk step. Notice: the desk sees Take Ownership where the customer saw nothing. Who sees which buttons depends on who owns the step, not on the view. Do not select it.

The manager’s report (no stop, screenshot only). Support Manager opens the Performance Report from the sidebar, on the web.

Screenshot pending The Performance Report open as Support Manager: a table of tickets with number, title, status, assignee, start and end dates What to notice: a report is a printable table built from a saved query; it opens on the web only, which matters for a manager who wants it on her phone.

When you finish, sign in again as Customer One in the private window for the next sessions.

What you sawThe building blockWhat the analyst specifies for it
Ticket Request, Incoming RequestsViews and their facesWho each screen is for, what it shows, what people can do there
A ticketAn entry of Support TicketsThe fields, their kinds and rules
The side panel and its stepsThe workflowSteps, owners, actions, field rules, time limits
The bellNotifications sent by reactionsWho is told what, and when
The doughnut chartA summary on a dashboardThe figure, its grouping, who sees it
Performance ReportA reportIts rows, columns, schedule and readers

⛏ Lab (38 min) — Objectives, scope and platform fit (BRD A3, A4, A5)

Section titled “⛏ Lab (38 min) — Objectives, scope and platform fit (BRD A3, A4, A5)”

Goal. Three sections of the BRD that tell the sponsor what success looks like, what the project will and will not deliver, what the platform can do for each need, and who the system is for.

Before you start. Your binder at version 0.1. The case file open at the charter (scope, people, success measures), the memo, the Release 2 requests and the glossary.

With a facilitator. You write alone; the facilitator circulates and asks, of any objective, “how would Mariam check that in month two?”. On your own. Ask yourself the same question of each objective before you compare.

A3: objectives and success measures

  1. Write four objectives, O-1 to O-4, one for each of the charter’s success measures SM-1 to SM-4. Use a table: No. · Objective · For whom · Success measure. Each objective says what changes and for whom; the last column quotes the charter’s measure.
  2. Below the table, write one sentence about any figure the case file mentions that is not a success measure, and say where it belongs instead.

A4: scope and platform fit

  1. Write the scope as four short lists: In scope, Release 1; In scope, Release 2; Out of scope; Later. Take them from the charter; “Later” may stay empty for now.

  2. Add the assumptions and constraints the charter and the glossary state (working hours, staff, who builds).

  3. Write the platform-fit table, Need · Verdict · How, or the workaround, for these twelve needs. For Configure, name the building block; for Not available, a workaround or a scope note.

    1. Customers can open and follow tickets from their phone.
    2. Every ticket gets its own number, without anyone typing it.
    3. The desk is told as soon as a new ticket arrives.
    4. A ticket goes from the desk to a representative and back to the desk.
    5. The support manager sees a chart of tickets by status.
    6. The support manager receives a PDF of all tickets by email on the 28th of each month.
    7. Weekends and public holidays do not count against the 4-hour pickup target.
    8. A customer can use the portal in Arabic.
    9. Customers earn reward points each time they rate the service.
    10. The support manager opens the monthly report on her phone between meetings.
    11. Tickets are routed automatically by the representatives’ HR skills profiles.
    12. If two desk agents act on the same ticket at the same time, one does not silently undo the other.

A5: stakeholders

  1. Copy the five-row stakeholder table from the concept into A5.
  2. Add a row for each of the three groups in the charter’s people table that it lacks: the account managers, the quality officer and IT (the builder and the administrator). Fill in their role, main need and what they approve.

Check.

  • Each objective names what changes and for whom, and points to one charter measure; you invented no figure.
  • Scope has both releases, repeats the charter’s three out-of-scope items, and has a “Later” list.
  • Every Configure names a building block you could point to on the tour.
  • Every Not available has a workaround or a scope note, not just “no”.
  • A5 has eight rows, and the approvals sit with the people the charter says decide.

Pass condition. Every box is ticked, at least 10 of your 12 verdicts match the reference, and every disagreement is written down with its reason.

If something goes wrong

What you seeWhat to do
An objective has no measureFind the charter measure it serves. If none fits, it is probably a requirement, not an objective.
You wrote “solved within 2 working days” as a success measureThat figure is the representatives’ (case file C), not the sponsor’s. It becomes a requirement in M1-S2.
You are torn between Ready-made and ConfigureAsk: does a builder have to choose anything? If yes, it is Configure.
You marked 10 or 11 as ConfigureRe-read Three answers: those limits are stated there.
You do not know what IT approvesNothing: the builder sizes changes and says what is feasible, the administrator sets up what the hand-off list asks.

From the hand-out: the three Release 2 rows of A5, which come from the case file’s Release 2 requests. File them under your eight rows.

StakeholderRole in the systemMain needApproves
Office managers at business customers (Release 2)Open tickets and visits for their staff; see their account’s ticketsAct for their staff—
Field engineers (Release 2)Agree visit dates, visit, recordTheir own visits, by date, on the phone—
Visitors (Release 2)Ask before buying, without an accountA simple form and an answer by email—
Model answer

A3. Objectives and success measures

No.ObjectiveFor whomSuccess measure (charter)
O-1From Release 1, every request has a number and an owner; none is lost.Customers, the deskSM-1: of 20 emails and calls picked at random each month, every one has a ticket number.
O-2New tickets are picked up quickly and predictably.CustomersSM-2: nine in ten new tickets are picked up within 4 working hours.
O-3Customers know where their request stands without asking.CustomersSM-3: of 20 solved tickets picked at random each month, every customer received the “received” and the “solved” messages.
O-4The support manager sees how support performs without counting.Support manager, sponsorSM-4: the monthly ticket report arrives by the 28th every month; the status chart is available at any moment.

Figures not given by the sponsor are not invented. The solving target of 2 working days is the representatives’ own figure (case file C); it becomes a requirement, not a success measure.

A4. Scope

  • In scope, Release 1 (week 10): customers open and follow tickets; the desk routes and checks them; refunds and replacements are approved by the support manager; customers are told and asked to rate; figures and a monthly report. Release 1 replaces the pilot and the spreadsheet.
  • In scope, Release 2 (week 18): customer accounts with a tier, site visits, the public pre-sales form, office managers acting for their staff, the quality officer, one list of open work.
  • Out of scope: the refund payment itself; Sales’ product catalogue; the telephone system.
  • Later: none yet.
  • Assumptions and constraints: working hours are Sunday to Thursday, 08:00 to 16:00, public holidays excluded; no new staff; the builder and the administrator come from IT.

In M1-S2 each scope line gets the requirement IDs it covers, and “Later” gets its first entries at sign-off and in the week after.

#NeedVerdictHow, or the workaround
1Open and follow tickets by phoneReady-madeThe mobile app shows the same screens; nothing extra to build once the views exist.
2A number for every ticketConfigureA running number on the ticket.
3The desk told of a new ticketConfigureAn automatic notification when a ticket reaches the desk.
4Desk to representative and backConfigureA workflow with steps, owners and actions.
5Status chartConfigureA chart on the desk’s and the manager’s screen.
6PDF by email on the 28thConfigureA scheduled report, sent as a PDF or an Excel file.
7Weekends and holidays not countedConfigureTime limits on workflow steps, against the administrator’s working hours and holidays.
8The portal in ArabicReady-madeEach person chooses the language; names are entered in both.
9Reward pointsNot availableNo points or game features. Scope note: out of scope. If the need is “more customers rate us”, a reminder is configurable.
10The report on her phoneNot availableReports open on the web only. Workaround: the emailed file, and the status chart, which works on the phone.
11Routing by skills profilesNot availableNo skills profiles. Workaround: the desk chooses the representative, as today.
12Two agents at onceReady-madeOnly the first action counts; the second person is told the record changed.

Why 10 and 12 are the ones people miss: 10 sounds like a mobile question (and the app is ready-made), but reports are the exception; 12 sounds like something to design, but the platform already protects it.

A5. Stakeholders and users: the five rows of the concept, then:

StakeholderRole in the systemMain needApproves
Account managers (Release 2)Look after business customersKnow how their accounts are served—
Quality officer (Ziad Amin, Release 2)Follows every site visitSee every visit, act on none—
IT: builder (Rania Saleh), administrator (Tariq Mansour)Build; set up groups and working hoursA blueprint and a hand-off list without gaps—

The reference also names the people in the rows you copied: the support manager is Salma Idris and she approves site visits too from Release 2; the director is Mariam Khalil.

  • BRD draft: A0, A1 (version 0.1), and now A3 (O-1 to O-4), A4 (scope, assumptions, platform fit for twelve needs), A5 (eight rows written, three filed from the hand-out).
  • A4’s “Later” list exists, even if empty.

Compare with the model answer and the hand-out above, sections A3 to A5.

✓ Practice (6 min) — Check your understanding

Section titled “✓ Practice (6 min) — Check your understanding”
PracticeChoose one answer.

A draft BRD says: “The Help Desk step is owned by the Technical Support Office group with Take Ownership.” What is wrong with it?

  1. Explanation for A

    ✓ Correct

    Correct: the BRD states the need in business words; the blueprint turns it into the builder’s options. See Two documents.

  2. Explanation for B

    ✗ Incorrect

    Not this one: the BRD is for the business and uses their words; option names belong in the blueprint. See Two documents.

  3. Explanation for C

    ✗ Incorrect

    Not this one: who owns the step is a design choice, and the case file asks for the whole desk. The problem is where the sentence sits. See Design depth.

Check your answer

The correct answer is A. Open the explanation under each option to see why.

Scenario

Mariam’s objective O-3 reads: “Customers know where their request stands without asking.” A colleague proposes three ways to show in month two that it was met.

PracticeChoose one answer.

Which one is a success measure for O-3?

  1. Explanation for A

    ✗ Incorrect

    Not this one: it names no count, no target and no way to check it from the system, so nobody could say it was met. See Objectives and success measures.

  2. Explanation for B

    ✗ Incorrect

    Not this one: that is a requirement about what the system does, not a check that the objective was reached. See Objectives and success measures.

  3. Explanation for C

    ✓ Correct

    Correct: it says what is counted, the target and how it is checked from the system; it is the charter’s SM-3. See Objectives and success measures.

Check your answer

The correct answer is C. Open the explanation under each option to see why.

Scenario

At a workshop, the support manager asks: “Can I have the monthly report on my phone, and can the finance team get it as a CSV file?”

PracticeChoose one answer.

What do you write in the BRD’s platform-fit table?

  1. Explanation for A

    ✗ Incorrect

    Not this one: reports open on the web only and export to PDF or Excel, so promising either would be a wrong yes. See Three answers.

  2. Explanation for B

    ✓ Correct

    Correct: you record the limits honestly and meet the real need another way; if finance needs a list of tickets, a list’s Export Entries can give CSV. See Three answers.

  3. Explanation for C

    ✗ Incorrect

    Not this one: an analyst who stays silent lets the business assume a yes; record the limit and an alternative now. See Three answers.

Check your answer

The correct answer is B. Open the explanation under each option to see why.

PracticeChoose every answer that applies.

During the tour, which of these did you see that a builder had configured (not ready-made)? Select all that apply.

  1. Explanation for A

    ✓ Correct

    Correct: a builder created the summary and turned on the view’s dashboard as its landing screen. See the tour.

  2. Explanation for B

    ✓ Correct

    Correct: the builder chose a group owner with Take Ownership for the Help Desk step. See the tour.

  3. Explanation for C

    ✗ Incorrect

    Not this one: once views exist, the app shows them with no extra work; that is ready-made. See Three answers.

Check your answer

The correct answers are A and B. Open the explanation under each option to see why.

PracticeChoose one answer.

The memo asks for “figures on how quickly we solve problems”, but neither the memo nor the charter gives a target for solving. What do you write in A3?

  1. Explanation for A

    ✗ Incorrect

    Not this one: targets belong to the sponsor; inventing one hides a decision nobody made. See Objectives and success measures.

  2. Explanation for B

    ✗ Incorrect

    Not this one: that is one team’s own estimate, so it becomes a requirement; it is not a target the sponsor set. See Objectives and success measures.

  3. Explanation for C

    ✓ Correct

    Correct: the objective is written, and the missing number is recorded as a decision the sponsor still owes. See Objectives and success measures.

Check your answer

The correct answer is C. Open the explanation under each option to see why.

You can say what goes into the BRD, its sub-documents and the blueprint, write objectives that point to the sponsor’s measures, recognise each building block of a delivered system, and answer “will the platform do it?” honestly, with a workaround when the answer is no.