M1-S2 — Govern the program: owners, environments, releases and decisions

Section titled “M1-S2 — Govern the program: owners, environments, releases and decisions”
ModuleM1 — Lead the enterprise program
After this session you canSet up a program’s module ownership, environments and promotion path, release train against platform upgrades, change control and decision records.
TimeFacilitated: 64 min · On your own: 61 min
Before you startM1-S1: your larkspur-program.md with its inventory and risk register. Larkspur Dev as Rami Aziz.
Go deeperEnvironments and promotion · Package schema versioning · Maintenance operations

◆ Orientation (1 min) — Turning responses into rules

Section titled “◆ Orientation (1 min) — Turning responses into rules”

Your register from M1-S1 ends in a column of responses: name an owner, agree who may change the supplier rating, package Quality before anyone changes it. Each is a one-off fix. Governance is what stops the same risks from coming back the next time a team changes something: a small set of agreements about who owns what, how changes travel, when they travel, and how the reasons are kept.

You leave this session with Larkspur’s governance plan and its first three decision records. The capstone asks you to apply the same plan to a new module (M11-S1), and the upgrade plan in M9-S2 runs on the release train you define here.

▤ Concept (13 min) — Five agreements that keep a program working

Section titled “▤ Concept (13 min) — Five agreements that keep a program working”

A program needs five agreements, and a gate that makes them real. None is a product feature; each uses product features. Write them down, keep them short, and change them by the same change control they define.

Every module has one named owner: a person, not a team, who approves changes to its design and answers for it in production. The owner may delegate building to others, but there is one name. On Larkspur that means four names, recorded in each module’s description (the platform has no owner field, so the program agrees where it is written) and matched by the module’s Permissions tab: the owner and the people they choose hold Developer or Edit there, nobody else.

A shared seam is anything in one module that another module relies on: a field read through a proxy, a value list another module routes by, an event another module reacts to. M1-S1 showed you how to find them. Governance turns them into a seam register, one line per seam: the owning module, the field or event, its normalized name and values, and the modules that depend on it. A seam on the register can change only with the agreement of every dependent module’s owner. A change that touches nothing on the register needs only its own module’s owner. That one rule would have prevented every coupling risk in your register.

Ownership also decides who holds design rights where. In Development, each module’s owner grants Developer or Edit to the builders they choose. In Test and Production nobody needs design rights at all, because nobody changes designs there by hand: installing a package version is done by the program’s release process, under an administrator’s identity that exists for that purpose (you meet it, and the risk it carries, in M6-S3). A person who holds Developer in Production is an exception to explain, not a convenience.

An environment is a separate place where the suite runs: its own space (or tenant), its own users and credentials, its own data. A program needs at least three, each with one purpose.

EnvironmentPurposeWho changes the design thereLarkspur
DevelopmentTeams build and try changesEach module’s buildersLarkspur Dev
TestAll modules’ next versions meet, on the next platform version, with realistic data; acceptance is run hereNobody by hand: only promotionLarkspur Lab
ProductionPeople workNobody by hand: only promotionLarkspur’s production tenant (Larkspur Lab stands in for it in the capstone)

Promotion is how a change moves from one environment to the next, and on Osos it moves as a package version. You built and installed package versions in ACE M8-S1: a version is a fixed snapshot of a module’s design, with release notes, that a target installs or updates to. The governance rule built on it is simple: the design of Test and Production is changed only by installing a package version that was built in Development. Nobody edits a view in production “just this once”. If a fix is urgent, it is a small-fix version, built in Development and promoted the same day.

flowchart LR
  D["Development<br/>build, try"] -->|"package version<br/>+ release notes"| T["Test<br/>install, acceptance,<br/>dependents checked"]
  T -->|"the same version,<br/>unchanged"| P["Production<br/>install in the window"]
  P -.->|"hotfix starts again<br/>in Development"| D

What to notice: the same version file goes to Test and to Production. If what reaches Production differs from what passed in Test, the test proved nothing.

What a package cannot carry still has to reach each environment: application users and their tokens, function secret values, addresses inside reactions, sign-in clients and grants that depend on the target’s groups. ACE called the list for one release a promotion plan (ACE M8-S1). In a program, the promotion plan is a standing document per module, updated with each release, and the Test install is where it is proved: if a step was missed, the Test acceptance fails, not Production.

3. The release train, and platform upgrades

Section titled “3. The release train, and platform upgrades”

Four teams releasing whenever they are ready means four different combinations of module versions in Test at any moment, and a platform upgrade arriving in the middle. A release train fixes the rhythm instead: on a known cadence (for example every two weeks), every module that has a release ready puts it on the train; the train is installed in Test together, accepted together, and installed in Production together in an agreed window. A team that misses the train waits for the next one. Nobody is blocked for long, and Test always holds one known combination.

Platform upgrades travel on the same rails, in their own slot. Two facts about packages make the order matter. Each package records the platform release that exported it; installing it into an environment on an older platform release raises a warning that the package may use something that environment lacks. And the package format itself has versions: an older platform refuses a format version it does not know. Both checks are explained in M6-S2; the governance rule they lead to is: upgrade environments in promotion order, Test before Production, and never promote a package from an upgraded environment into one that has not been upgraded yet. So the upgrade train looks like this: upgrade Test; run the whole suite’s acceptance on it; hold module releases for that train (nothing else changes while the platform does); upgrade Production in its window; then upgrade Development, so new packages are built on the release Production now runs. M9-S2 turns this into a full upgrade plan with its checks and the limits of rolling back.

Not every change deserves a meeting. Classify each change by what it can break, and let the class decide who approves it.

ClassWhat it touchesWho approvesEvidence required
A: Inside a moduleThe module’s own design, nothing on the seam registerThe module’s ownerBuilt in Development; release notes
B: A shared seamAnything on the seam register: a shared field’s normalized name, type or values, a shared eventThe owner, every dependent module’s owner, and the program ownerThe dependency graph’s dependents for the changed resource; every dependent checked in Test
C: The platformA platform upgrade; an extension (a Function, an outside integration, a credential); who may change designsThe program owner, with the sponsor or the operator as relevantA plan, the threat model where security changes (M5-S4), a rollback limit stated

A change’s class is decided by what it touches, not by how small it looks. The Seals split in M1-S1’s scenario looked like a Class A label change; it was Class B because of its values.

Every train passes one gate before Production: acceptance in Test. Each module keeps a standing acceptance list: the checks that prove it still does its job, written as in ACA, as observable pass or fail statements (“a purchase request above 25,000 reaches Technical Review; one of 4,000 does not”). The list grows with every release, because each fix adds the check that would have caught the problem. A train passes when every module on it passes its own list and every dependent of a changed seam passes the checks that touch the seam.

Check typeExample on LarkspurWho runs it
A module’s own behaviourA work order raised by the nightly plan appears with the right asset titleThe module’s builders
A seam’s dependentsA non-conformance against a Seals supplier is owned by the seals specialistThe dependent module’s builders
What the package could not carrySend approved order to ERP reaches Test’s ERP stub, not production’sThe program owner, from the promotion plan
The platformThe smoke test of the release, after an upgradeThe operator

A train that fails acceptance does not go to Production, in part or in whole, until the failing module is fixed or taken off the train. Taking a module off is allowed only when nothing else on the train depends on its new version.

A decision record is a short, dated note of one significant decision: what was decided, why, what else was considered, and what follows from it. It exists for the next owner, who will otherwise undo a good decision because its reason was never written down, or keep a bad one because nobody dares to touch it.

SectionWhat it holds
Id, title, date, statusDR-004 Quality and Compliance is promoted like every other module, 2026-11-23, accepted (or proposed, superseded by DR-…)
ContextThe facts that forced a decision, with evidence: the register row it answers
DecisionOne or two sentences, in the active voice: “We will …”
AlternativesThe options considered and why each was not chosen
ConsequencesWhat becomes easier, what becomes harder, what must now be done, and by whom

Records are never edited once accepted: a changed mind is a new record that supersedes the old one. Keep them with the program’s documents, numbered, in one place. Write one when a decision is hard to reverse, affects more than one module, or was argued about. Do not write one for a Class A change.

◇ Worked scenario (3 min) — The urgent fix on a Thursday

Section titled “◇ Worked scenario (3 min) — The urgent fix on a Thursday”

It is Thursday afternoon. Purchase requests above 25,000 are not reaching the technical review: the condition on the Procurement workflow compares the total against the wrong field. Sara Qasim’s builder has found the mistake and wants to correct the condition directly in production, “two clicks, nothing else changes”. The next train is in nine days. Decide at each point.

Decision 1: which class is it?

The condition is inside Procurement’s workflow and touches nothing on the seam register. Class A: Sara approves. Its smallness does not change the class; the class only says who approves.

Decision 2: may it be fixed in production by hand?

No, and you explain why in one sentence: a hand edit in production makes production differ from the version Test accepted and from the package the team will build next, and the next promotion would silently undo it, or be refused because the installed parts no longer match the package. The promotion rule has no “just this once”, because every exception is the one nobody remembers.

Decision 3: does it wait nine days?

Not necessarily. The train sets the normal rhythm; an urgent fix can travel alone if it follows the same path. The builder corrects the condition in Development and builds Procurement 2.0.2, a Small fix version with release notes. You install it in Test; a test purchase request of 30,000 reaches the technical review, and one of 4,000 does not; the rest of Procurement’s acceptance is run. You install the same file in Production that evening.

Decision 4: what is written down?

The release notes say what changed. No decision record is needed: it is a Class A fix following the rules. But you add one line to the program’s “lessons” list: the workflow’s threshold should have had an acceptance test that would have caught the wrong field, and Procurement’s acceptance list gains it.

The outcome. The fix reaches production in four hours, through Test, as a version anyone can see and repeat. The governance plan did not slow the fix down; it made the fix safe.

⛏ Lab (28 min) — Larkspur’s governance plan and its first three decisions

Section titled “⛏ Lab (28 min) — Larkspur’s governance plan and its first three decisions”

Goal. A governance plan for Larkspur covering the five agreements, the start of the seam register, Quality and Compliance exported as its first package version, and three decision records.

Before you start. larkspur-program.md from M1-S1. A new document larkspur-governance.md. Larkspur Dev as Rami Aziz, with Developer access to Quality and Compliance (you are system Admin).

Owners and seams

  1. Under a heading Owners, name one owner per module. Where M1-S1 found none (Supplier Management, Quality and Compliance), propose the person and note that Leila Amari must confirm.
  2. Under Seam register, write one line for each shared seam your seam map shows: owning module, resource and normalized name, values where they matter, and dependent modules. Include at least the supplier Rating, the supplier Category and its values, and Approved Suppliers.

Environments, promotion and the train

  1. Under Environments, fill the three-environment table for Larkspur, naming each environment’s purpose and who may change designs there.
  2. Under Promotion, write the promotion rule in one sentence, and list the standing promotion-plan items for Procurement (at least: the Legacy ERP Sync decision from R-02, the ERP address in Send approved order to ERP, and any group the workflow’s owners depend on).
  3. Under Release train, set the cadence, the day Test is installed, the Production window, and the order of a platform upgrade across the three environments.

Change control

  1. Under Change control, adapt the three classes to Larkspur, and classify these four changes: a new view in Asset Maintenance; a new value Hydraulics in the supplier Category; a new application user for a supplier portal; a renamed label on Work Orders › Priority.

The first package version of Quality and Compliance

  1. In Larkspur Dev, open Administration › Packages › Build, on the Packages tab create a package larkspur-quality-compliance containing the Quality and Compliance module.

  2. Read its External dependencies before creating a version: note each one (you expect Supplier Management’s suppliers, read through Audited Suppliers) and how an installer must map it.

  3. Select Create version, choose Big change for a first version, write Release notes that say this is the production baseline, and create 1.0.0.

    Screenshot pending The Create version dialog for the larkspur-quality-compliance package, with Big change selected and release notes filled in What to notice: the version is fixed once created; any later change to Quality and Compliance travels as a new version.

Acceptance

  1. Under Acceptance, write Procurement’s standing acceptance list: at least four pass-or-fail checks, including one for the technical-review threshold and one for each dependent of Approved Suppliers.

Decision records

  1. Write DR-001 Shared seams change only with their dependents’ owners, answering R-01.
  2. Write DR-002 Quality and Compliance is promoted like every other module, answering R-03, with step 9’s version as its evidence.
  3. Write DR-003 on a decision of your choice that your plan makes (for example: the release train’s cadence, or retiring Legacy ERP Sync).
  4. Check each record against the five sections, and give each a status (proposed until the owners named in it agree).

Check.

  • Every module has one named owner, or a proposed one marked for confirmation.
  • The seam register lists at least three seams with their dependents.
  • The plan states the promotion rule, the standing promotion-plan items for Procurement, the train’s cadence and the upgrade order Test, Production, Development.
  • The four example changes are classified, with the reason for each.
  • larkspur-quality-compliance 1.0.0 exists in Larkspur Dev, and its external dependencies are noted.
  • Procurement’s acceptance list has at least four pass-or-fail checks, one of them for a dependent of Approved Suppliers.
  • Three decision records, each with context, decision, alternatives, consequences and a status.

Pass condition. All seven checks hold, and the classification puts the new Hydraulics value in Class B and the new application user in Class C.

If something goes wrong

What you seeWhat to do
Create version is greyed outThe package has an unresolved external dependency that blocks it, or no module selected. Read the Contents tab; for this lab, a dependency on Supplier Management’s suppliers is expected and is resolved by the installer’s mapping.
The package cannot include Quality and ComplianceA module belongs to only one package; check under Packages whether another package already holds it.
You are unsure whether a change is Class A or BLook for its resource in the seam register. If it is there, or the dependency graph lists dependents for it, it is Class B.
Your decision record runs past a pageIt probably holds several decisions. Split it; one decision per record.
Model answer

Owners. Supplier Management: proposed Sara Qasim (Procurement uses it most; confirm with Leila Amari). Procurement: Sara Qasim. Asset Maintenance: Omar Haddad. Quality and Compliance: proposed Tariq Saleh.

Seam register (start).

SeamOwnerNormalized name and valuesDependents
Supplier ratingSupplier Managementrating, number 0 to 5Quality (writes it through Audited Suppliers; Supplier Scorecard)
Supplier categorySupplier Managementcategory: Bearings, Seals, Castings, ValvesProcurement (Approved Suppliers), Quality (owner routing, Supplier Scorecard)
Approved SuppliersProcurementproxy of Suppliers: supplier_name, category, ratingAsset Maintenance (Spare Parts)

Environments and promotion. As in the Concept’s table. Rule: the design of Test and Production changes only by installing a package version built in Development. Procurement’s standing items: decide and recreate (or retire) the ERP application user per environment; set the ERP address in Send approved order to ERP per environment; check the groups the workflow’s owners use exist in the target.

Release train. Every second Tuesday into Test, acceptance Wednesday and Thursday, Production window the following Monday evening. Platform upgrade: Test first, full acceptance, module releases held for that train, Production in its window, then Development.

Classification. New view in Asset Maintenance: A (inside one module). Hydraulics in Category: B (a shared value list that Quality routes by and two modules read). New application user: C (a new credential and integration). Renamed Priority label: A (a label, not a normalized name or a value, and Priority is on no seam).

Procurement’s acceptance list (start). A purchase request of 30,000 reaches Technical Review; one of 4,000 goes straight to procurement approval. An approved order reaches the ERP stub of the environment it runs in. The supplier picker on a purchase request offers only approved suppliers, with their category. A spare part in Asset Maintenance still shows its supplier’s name (the dependent of Approved Suppliers).

DR-001, in outline. Context: R-01; Quality writes ratings into Supplier Management; the category split nearly broke routing. Decision: “We will keep a seam register; a change to a registered seam needs the agreement of every dependent module’s owner and a check of each dependent in Test.” Alternatives: forbid all cross-module writes (rejected: the rating chain is valuable); let owners decide alone (rejected: that is today’s risk). Consequences: Class B changes take longer; the seam register must be kept current at each train; Supplier Management’s owner gains a duty to consult. Status: proposed.

DR-002 records the 1.0.0 baseline as evidence and the consequence that Quality’s next change goes through Development and Test. Your DR-003 passes if it has all five sections and one decision.

✳ Discussion (10 min) — Who may change a shared seam?

Section titled “✳ Discussion (10 min) — Who may change a shared seam?”

Omar Haddad’s team wants a new field on Approved Suppliers, Procurement’s proxy, so spare parts can show each supplier’s lead time. Procurement owns the proxy; Supplier Management owns the field underneath; Asset Maintenance is the one asking. Your DR-001 says registered seams change only with every dependent owner’s agreement.

With a facilitator: groups of three, each member taking one owner’s side (Supplier Management, Procurement, Asset Maintenance), for six minutes: agree who decides, what is checked, and whether the rule in DR-001 is too heavy for this case. Then four minutes in plenary: each group gives its verdict and the one condition it would add to DR-001.

On your own: write two short answers. (1) Who approves this change, and what evidence do you ask for before it ships? (2) Is DR-001 too heavy for adding a field, as opposed to changing one? If so, how would you amend it without losing its protection?

Model answer

(1) Adding the lead time touches two registered seams: Supplier Management must add or expose the field (its owner approves, because others will now rely on it), and Procurement must add it to Approved Suppliers (its owner approves). Asset Maintenance’s owner is the requester, not an approver. Evidence: the field added in Development with its normalized name agreed (lead_time_days) and entered on the seam register, the dependency graph showing the new dependent, and a Test check that existing dependents (Quality’s scorecard and routing) still work.

(2) DR-001 is heavier than needed for a pure addition, because nothing existing can break when a field is added. A reasonable amendment, written as a new record that supersedes DR-001: additions to a seam need only the owning module’s owner and an entry on the seam register; changes and removals need every dependent’s owner. The protection is kept because the register still records who now depends on the new field, so its later change is controlled.

PracticeChoose one answer.

A builder wants to fix a typo in a production view’s title directly in Production, saying nothing else changes. What does the promotion rule say, and why?

  1. Explanation for A

    ✗ Incorrect

    Not this one: a view’s title is part of its design and travels in the package, so the next promotion would bring back the typo. See The promotion path.

  2. Explanation for B

    ✗ Incorrect

    Not this one: approval decides who may change a design, not where; the change still has to travel as a version. See Change control.

  3. Explanation for C

    ✓ Correct

    Correct: hand edits make Production differ from every package, and the next install undoes or conflicts with them. See The promotion path.

Check your answer

The correct answer is C. Open the explanation under each option to see why.

PracticePut the items in the right order.

Put a platform upgrade of the Larkspur environments in the order the release train sets.

  1. Explanation for A

    Belongs in position 4 of 4

    Last: a package built on a newer release than its target raises warnings or is refused, so Development follows Production. See The release train.

  2. Explanation for B

    Belongs in position 1 of 4

    First: Test is where the new release meets every module’s next version, and acceptance proves it before anyone depends on it. See The release train.

  3. Explanation for C

    Belongs in position 3 of 4

    Third: Production receives the release only after Test has accepted the whole suite on it. See The release train.

  4. Explanation for D

    Belongs in position 2 of 4

    Second: while the platform changes, nothing else changes, so a failure has one cause to look for. See The release train.

Check your answer

The correct order is B → D → C → A. Open the explanation under each item to see why it sits where it does.

PracticeChoose one answer.

Development was upgraded first by mistake, and a team exports Procurement 2.1.0 from it. Production is still on the older platform release. What happens if the version is installed there?

  1. Explanation for A

    ✓ Correct

    Correct: a newer source release is a warning, a format version the older platform does not know is a refusal. See The release train.

  2. Explanation for B

    ✗ Incorrect

    Not this one: each package records the release that exported it, and the importer compares it with its own. See The release train.

  3. Explanation for C

    ✗ Incorrect

    Not this one: an import never upgrades the platform; upgrades are the operator’s release. See The release train.

Check your answer

The correct answer is A. Open the explanation under each option to see why.

PracticeChoose one answer.

Which change is Class B in Larkspur’s change control?

  1. Explanation for A

    ✗ Incorrect

    Not this one: it is inside one module and on no seam, so its owner approves it alone. See Change control.

  2. Explanation for B

    ✓ Correct

    Correct: the rating is a registered seam that Quality writes and reports on, so every dependent’s owner must agree. See Owners and seams.

  3. Explanation for C

    ✗ Incorrect

    Not this one: a new extension and outside integration is a platform-level change, Class C. See Change control.

Check your answer

The correct answer is B. Open the explanation under each option to see why.

PracticeChoose one answer.

A year from now, a new master finds DR-001 and disagrees with it. What should happen?

  1. Explanation for A

    ✗ Incorrect

    Not this one: accepted records are never edited; the history of why things changed would be lost. See Decision records.

  2. Explanation for B

    ✗ Incorrect

    Not this one: deleting removes the reason the program worked this way, which is what records exist to keep. See Decision records.

  3. Explanation for C

    ✓ Correct

    Correct: a changed decision is a new record, and the old one is marked superseded. See Decision records.

Check your answer

The correct answer is C. Open the explanation under each option to see why.

PracticeChoose one answer.

The Asset Maintenance team missed this train’s cut-off by one day with a finished release. What does the train say?

  1. Explanation for A

    ✓ Correct

    Correct: the train keeps Test on one known combination; urgent fixes still go Development, Test, Production. See The urgent fix on a Thursday.

  2. Explanation for B

    ✗ Incorrect

    Not this one: Test would then hold a combination that was not planned, and acceptance would be rerun mid-train. See The release train.

  3. Explanation for C

    ✗ Incorrect

    Not this one: skipping Test removes the only place the combination of versions is accepted. See The promotion path.

Check your answer

The correct answer is A. Open the explanation under each option to see why.

↺ Recap (1 min) — After Module 1 you can

Section titled “↺ Recap (1 min) — After Module 1 you can”

After this module you can take over a running multi-module suite: inventory it, register its risks with evidence, and govern it with named owners, a seam register, environments and a promotion path, a release train that schedules platform upgrades, three classes of change control and decision records.

Next. In M2 you open the platform itself. You have governed the suite from the outside; now you follow one Larkspur request from the gateway to the stored record, so that every rule you just wrote rests on knowing what the platform does.